FAR 52.232-15 Progress Payments Not Included

Clause Federal Acquisition Regulation Apr 1984 version

Facts

Citation
FAR 52.232-15
Type
Clause
Current version
April 1984
Prescribed in
FAR 32.502-3(c)
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 32.502-3(c), insert the following provision in invitations for bids if the solicitation will not contain one of the provisions prescribed in 32.502-3 (a) and (b):

Progress Payments Not Included (Apr 1984)

A progress payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award. Bids conditioned upon inclusion of a progress payment clause in the resulting contract will be rejected as nonresponsive.

(End of clause)

Quick answers

What is FAR 52.232-15?

FAR 52.232-15 is a clause of the Federal Acquisition Regulation, titled "Progress Payments Not Included".

What is the current version of FAR 52.232-15?

The current version is dated April 1984.

Where is FAR 52.232-15 prescribed?

It is prescribed in FAR 32.502-3(c), Solicitation provisions.

Are changes to FAR 52.232-15 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract