FAR 52.228-16 Performance and Payment Bonds-Other Than Construction

Clause Federal Acquisition Regulation Nov 2006 version

Facts

Citation
FAR 52.228-16
Type
Clause
Current version
November 2006
Prescribed in
FAR 28.103-4
Alternates
Alternate I
Last amended
71 FR 67779 Effective Nov 22, 2006
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 28.103-4 , insert a clause substantially as follows:

Performance and Payment Bonds-Other Than Construction (Nov 2006)

(a) Definitions. As used in this clause-

"Original contract price" means the award price of the contract or, for requirements contracts, the price payable for the estimated quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) The Contractor shall furnish a performance bond (Standard Form 1418) for the protection of the Government in an amount equal to [fill-in] percent of the original contract price and a payment bond Standard Form 1416) in an amount equal to [fill-in] percent of the original contract price.

(c) The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within [fill-in] days, but in any event, before starting work.

(d) The Government may require additional performance and payment bond protection if the contract price is increased. The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bonds or to obtain additional bonds.

(e) The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register, or may be obtained from the:

U.S. Department of the Treasury,

Financial Management Service,

Surety Bond Branch,

3700 East West Highway,

Room 6 F01

Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(End of clause)

Alternate I

Alternate I (July2000). As prescribed in 28.103-4 , substitute the following paragraphs (b) and (d) for paragraphs (b) and (d) of the basic clause:

(b) The Contractor shall furnish a performance bond (Standard Form 1418) for the protection of the Government in an amount equal to [fill-in] percent of the original contract price.

(d) The Government may require additional performance bond protection if the contract price is increased. The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Technical Amendments 71 FR 67779 · FAC 2005-14
Federal Acquisition Regulation; Construction Industry Payment Protection Act of 1999 65 FR 46069 · FAC 97-19

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 91 FR 59534 · FAR Case 2026-010, Docket No. FAR-2026-0010, Sequence No. 1 Closed Oct 19, 2026No final rule found

Quick answers

What is FAR 52.228-16?

FAR 52.228-16 is a clause of the Federal Acquisition Regulation, titled "Performance and Payment Bonds-Other Than Construction".

What is the current version of FAR 52.228-16?

The current version is dated November 2006.

Where is FAR 52.228-16 prescribed?

It is prescribed in FAR 28.103-4, Contract clause.

When was FAR 52.228-16 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Technical Amendments" (71 FR 67779), published Nov 22, 2006 and effective Nov 22, 2006.

Are changes to FAR 52.228-16 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract