As prescribed in 19.708(b)(2), insert the following clause:
Liquidated Damages-Subcontracting Plan (Sep 2021)
(a) "Failure to make a good faith effort to comply with the subcontracting plan," as used in this clause, means a willful or intentional failure to perform in accordance with the requirements of the subcontracting plan approved under the clause in this contract entitled "Small Business Subcontracting Plan," or willful or intentional action to frustrate the plan.
(b) Performance shall be measured by applying the percentage goals to the total actual subcontracting dollars or, if a commercial plan is involved, to the pro rata share of actual subcontracting dollars attributable to Government contracts covered by the commercial plan. If, at contract completion or, in the case of a commercial plan, at the close of the fiscal year for which the plan is applicable, the Contractor has failed to meet its subcontracting goals and the Contracting Officer decides in accordance with paragraph (c) of this clause that the Contractor failed to make a good faith effort to comply with its subcontracting plan (see 19.705-7), established in accordance with the clause in this contract entitled "Small Business Subcontracting Plan," the Contractor shall pay the Government liquidated damages in an amount stated. The amount of probable damages attributable to the Contractor’s failure to comply shall be an amount equal to the actual dollar amount by which the Contractor failed to achieve each subcontract goal.
(c) Before the Contracting Officer makes a final decision that the Contractor has failed to make such good faith effort, the Contracting Officer shall give the Contractor written notice specifying the failure and permitting the Contractor to demonstrate what good faith efforts have been made and to discuss the matter. Failure to respond to the notice may be taken as an admission that no valid explanation exists. If, after consideration of all the pertinent data, the Contracting Officer finds that the Contractor failed to make a good faith effort to comply with the subcontracting plan, the Contracting Officer shall issue a final decision to that effect and require that the Contractor pay the Government liquidated damages as provided in paragraph (b) of this clause.
(d) With respect to commercial plans, the Contracting Officer who approved the plan will perform the functions of the Contracting Officer under this clause on behalf of all agencies with contracts covered by the commercial plan.
(e) The Contractor shall have the right of appeal, under the clause in this contract entitled, Disputes, from any final decision of the Contracting Officer.
(f) Liquidated damages shall be in addition to any other remedies that the Government may have.
(End of clause)
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation: Good Faith in Small Business Subcontracting |
Quick answers
What is FAR 52.219-16?
FAR 52.219-16 is a clause of the Federal Acquisition Regulation, titled "Liquidated Damages-Subcontracting Plan".
What is the current version of FAR 52.219-16?
The current version is dated September 2021.
Where is FAR 52.219-16 prescribed?
It is prescribed in FAR 19.708(b)(2), Contract clauses.
When was FAR 52.219-16 last changed?
The most recent final rule on record is "Federal Acquisition Regulation: Good Faith in Small Business Subcontracting" (86 FR 44249), published Aug 11, 2021 and effective Sep 10, 2021.
Are changes to FAR 52.219-16 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract