FAR 52.215-8 Order of Precedence-Uniform Contract Format

Clause Federal Acquisition Regulation Oct 1997 version

Facts

Citation
FAR 52.215-8
Type
Clause
Current version
October 1997
Prescribed in
FAR 15.209(h)
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 15.209(h), insert the following clause:

Order of Precedence-uniform Contract Format (Oct 1997)

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(a) The Schedule (excluding the specifications).

(b) Representations and other instructions.

(c) Contract clauses.

(d) Other documents, exhibits, and attachments.

(e) The specifications.

(End of clause)

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary FAR Overhaul Parts 8, 12, 13, 15, 38, 44, and 51 91 FR 59406 · FAR Case 2026-003, Docket No. FAR-2026-0003, Sequence No. 1 Closed Oct 19, 2026No final rule found

Quick answers

What is FAR 52.215-8?

FAR 52.215-8 is a clause of the Federal Acquisition Regulation, titled "Order of Precedence-Uniform Contract Format".

What is the current version of FAR 52.215-8?

The current version is dated October 1997.

Where is FAR 52.215-8 prescribed?

It is prescribed in FAR 15.209(h), Solicitation provisions and contract clauses.

Are changes to FAR 52.215-8 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract