FAR 49.603-5 Cost-reimbursement contracts-partial termination
Subsection Federal Acquisition Regulation
Facts
- Citation
- FAR 49.603-5
- Type
- Subsection
- Last amended
- 82 FR 4709 Effective Jan 13, 2017
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
[Insert the following in Block 14 of SF 30, Amendment of Solicitation/Modification of Contract, for settlement agreements for cost-reimbursement contracts as a result of partial termination.]
(a) This supplemental agreement settles the termination settlement proposal resulting from the Notice of Termination dated _________.
(b) The parties agree as follows:
(1) The contract is amended by deleting the terminated portion as follows: [specify the terminated portion clearly as to-
(i) Line item numbers,
(ii) Descriptions,
(iii) Quantity terminated,
(iv) Unit and total price of terminated items, and
(v) Any other explanation necessary to avoid uncertainty or misunderstanding].
(2) The fee stated in the contract is decreased by $, from $ to $____ [Insert, if appropriate,"(3) The estimated cost of the contract is decreased by $, from $ to $____"].
(c) The Contractor’s allowable costs and earned fee, if any, for the terminated portion of the contract will continue to be reimbursed on SF 1034, Public Voucher for Purchase and Services Other Than Personal, under the applicable provisions of the contract and part 31 of the Federal Acquisition Regulation.
(End of agreement)
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Uniform Use of Line Items |
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 | Closed Jul 23, 2026No final rule found |
Sections cited
- FAR Part 31 Contract Cost Principles and Procedures
Quick answers
What is FAR 49.603-5?
FAR 49.603-5 is a subsection of the Federal Acquisition Regulation, titled "Cost-reimbursement contracts-partial termination".
When was FAR 49.603-5 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Uniform Use of Line Items" (82 FR 4709), published Jan 13, 2017 and effective Jan 13, 2017.
Are changes to FAR 49.603-5 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract