FAR 49.504 Termination of fixed-price contracts for default
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 49.504
- Type
- Section
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a)
(1) Supplies and services. The contracting officer shall insert the clause at 52.249-8, Default (Fixed-Price Supply and Service), in solicitations and contracts when a fixed-price contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold. The contracting officer may use the clause when the contract amount is at or below the simplified acquisition threshold, if appropriate (e.g., if the acquisition involves items with a history of unsatisfactory quality).
(2) Transportation. If the contract is for transportation or transportation-related services, the contracting officer shall use the clause with its AlternateI.
(b) Research and development. The contracting officer shall insert the clause at 52.249-9, Default (Fixed-Price Research and Development), in solicitations and contracts for research and development when a fixed-price contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold, except those with educational or nonprofit institutions on a no-profit basis. The contracting officer may use the clause when the contract amount is at or below the simplified acquisition threshold;, if appropriate (e.g., if the contracting officer believes that key personnel essential to the work may be devoted to other programs).
(c)
(1) Construction. The contracting officer shall insert the clause at 52.249-10, Default (Fixed-Price Construction), in solicitations and contracts for construction, when a fixed-price contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold. The contracting officer may use the clause when the contract amount is at or below the simplified acquisition threshold, if appropriate (e.g., if completion dates are essential).
(2) Dismantling and demolition. If the contract is for dismantling, demolition, or removal of improvements, the contracting officer shall use the clause with its AlternateI.
(3) National emergencies. If the contract is to be awarded during a period of national emergency, the contracting officer may use the clause-
(i) With its AlternateII when a fixed-price contract for construction is contemplated, or
(ii) With its AlternateIII when a contract for dismantling, demolition, or removal of improvements is contemplated.
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 | Closed Jul 23, 2026No final rule found |
Sections cited
- FAR 52.249-8 Default (Fixed-Price Supply and Service)
- FAR 52.249-9 Default (Fixed-Price Research and Development)
- FAR 52.249-10 Default (Fixed-Price Construction)
Quick answers
What is FAR 49.504?
FAR 49.504 is a section of the Federal Acquisition Regulation, titled "Termination of fixed-price contracts for default".
Are changes to FAR 49.504 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract