FAR 49.403 Termination of cost-reimbursement contracts for default

Section Federal Acquisition Regulation

Facts

Citation
FAR 49.403
Type
Section
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) The right to terminate a cost-reimbursement contract for default is provided for in the Termination for Default or for Convenience of the Government clause at 52.249-6. A 10-day notice to the contractor before termination for default is required in every case by the clause.

(b) Settlement of a cost-reimbursement contract terminated for default is subject to the principles in subparts 49.1 and 49.3 the same as when a contract is terminated for convenience, except that-

(1) The costs of preparing the contractor’s settlement proposal are not allowable (see paragraph (h)(3) of the clause); and

(2) The contractor is reimbursed the allowable costs, and an appropriate reduction is made in the total fee, if any, (see paragraph (h)(4) of the clause).

(c) The contracting officer shall use the procedures in 49.402 to the extent appropriate in considering the termination for default of a cost-reimbursement contract. However, a cost-reimbursement contract does not contain any provision for recovery of excess repurchase costs after termination for default (but see paragraph (g) of the clause at 52.246-3 with respect to failure of the contractor to replace or correct defective supplies).

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 91 FR 37698 · FAR Case 2026-007, Docket No. FAR-2026-0007, Sequence No. 1 Closed Jul 23, 2026No final rule found

Sections cited

Quick answers

What is FAR 49.403?

FAR 49.403 is a section of the Federal Acquisition Regulation, titled "Termination of cost-reimbursement contracts for default".

Are changes to FAR 49.403 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract