FAR 49.208 Equitable adjustment after partial termination

Section Federal Acquisition Regulation

Facts

Citation
FAR 49.208
Type
Section
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

Under the termination clause, after partial termination, a contractor may request an equitable adjustment in the price or prices of the continued portion of a fixed-price contract. The TCO shall forward the proposal to the contracting officer except when negotiation authority is delegated to the TCO. The contractor shall submit the proposal in the format of Table 15-2 of 15.408.

(a) When the contracting officer retains responsibility for negotiating the equitable adjustment and executing a supplemental agreement, the contracting officer shall ensure that no portion of an increase in price is included in a termination settlement made or in process.

(b) The TCO shall also ensure that no portion of the costs included in the equitable adjustment are included in the termination settlement.

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 91 FR 37698 · FAR Case 2026-007, Docket No. FAR-2026-0007, Sequence No. 1 Closed Jul 23, 2026No final rule found

Sections cited

  • FAR 15.408 Solicitation provisions and contract clauses

Quick answers

What is FAR 49.208?

FAR 49.208 is a section of the Federal Acquisition Regulation, titled "Equitable adjustment after partial termination".

Are changes to FAR 49.208 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract