FAR 49.203 Adjustment for loss
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 49.203
- Type
- Section
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a) In the negotiation or determination of any settlement, the TCO shall not allow profit if it appears that the contractor would have incurred a loss had the entire contract been completed. The TCO shall negotiate or determine the amount of loss and make an adjustment in the amount of settlement as specified in paragraph (b) or (c) of this section. In estimating the cost to complete, the TCO shall consider expected production efficiencies and other factors affecting the cost to complete.
(b) If the settlement is on an inventory basis (see 49.206-2(a)), the contractor shall not be paid more than the total of the amounts in paragraphs (b)(1), (2), and (3) of this section, less all disposal credits and all unliquidated advance and progress payments previously made under the contract:
(1) The amount negotiated or determined for settlement expenses.
(2) The contract price, as adjusted, for acceptable completed end items (see 49.205).
(3) The remainder of the settlement amount otherwise agreed upon or determined (including the allocable portion of initial costs (see 31.205-42(c)), reduced by multiplying the remainder by the ratio of-
(i) The total contract price to
(ii) The total cost incurred before termination plus the estimated cost to complete the entire contract.
(c) If the settlement is on a total cost basis (see 49.206-2(b)), the contractor shall not be paid more than the total of the amounts in paragraphs (c)(1) and (2) of this section, less all disposal and other credits, all advance and progress payments, and all other amounts previously paid under the contract:
(1) The amount negotiated or determined for settlement expenses.
(2) The remainder of the total settlement amount otherwise agreed upon or determined (lines 7 and 14 of SF 1436, Settlement Proposal (Total Cost Basis)) reduced by multiplying the remainder by the ratio of-
(i) The total contract price to
(ii) The remainder plus the estimated cost to complete the entire contract.
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 | Closed Jul 23, 2026No final rule found |
Sections cited
- FAR 49.206-2(a) Bases for settlement proposals
- FAR 49.205 Completed end items
- FAR 31.205-42(c) Termination costs
Quick answers
What is FAR 49.203?
FAR 49.203 is a section of the Federal Acquisition Regulation, titled "Adjustment for loss".
Are changes to FAR 49.203 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract