FAR 49.108-1 Subcontractor’s rights
Subsection Federal Acquisition Regulation
Facts
- Citation
- FAR 49.108-1
- Type
- Subsection
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
A subcontractor has no contractual rights against the Government upon the termination of a prime contract. A subcontractor may have rights against the prime contractor or intermediate subcontractor with whom it has contracted. Upon termination of a prime contract, the prime contractor and each subcontractor are responsible for the prompt settlement of the settlement proposals of their immediate subcontractors.
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 | Closed Jul 23, 2026No final rule found |
Quick answers
What is FAR 49.108-1?
FAR 49.108-1 is a subsection of the Federal Acquisition Regulation, titled "Subcontractor’s rights".
Are changes to FAR 49.108-1 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract