FAR 47.207-2 Duration of contract and time of performance

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 47.207-2
Type
Subsection
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

The contracting officer shall-

(a) Establish a specific expiration date (month, day, and year) for the contract or state the length of time that the contract will remain in effect; *e.g.,*6 months commencing from the date of award; and

(b) Include the following items as appropriate:

(1) A statement of the time period during which the service is required when the service is a one-time job; *e.g.,*a routine office relocation.

(2) A time schedule for the performance of segments of a major job; e.g., an office relocation for which the work phases must be coordinated to meet other needs of the agency.

(3) Statements of performance times for particular services; e.g., pickup and delivery services. Specify-

(i) On which days of the week and during which hours of the day pickup and delivery services may be required;

(ii) The maximum time allowable to the contractor for accomplishing delivery under regular or priority service; and

(iii) How much advance notice the contractor will be given for regular pickup services and, if applicable, priority pickup services.

Quick answers

What is FAR 47.207-2?

FAR 47.207-2 is a subsection of the Federal Acquisition Regulation, titled "Duration of contract and time of performance".

Are changes to FAR 47.207-2 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract