FAR 47.207-2 Duration of contract and time of performance
Subsection Federal Acquisition Regulation
Facts
- Citation
- FAR 47.207-2
- Type
- Subsection
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
The contracting officer shall-
(a) Establish a specific expiration date (month, day, and year) for the contract or state the length of time that the contract will remain in effect; *e.g.,*6 months commencing from the date of award; and
(b) Include the following items as appropriate:
(1) A statement of the time period during which the service is required when the service is a one-time job; *e.g.,*a routine office relocation.
(2) A time schedule for the performance of segments of a major job; e.g., an office relocation for which the work phases must be coordinated to meet other needs of the agency.
(3) Statements of performance times for particular services; e.g., pickup and delivery services. Specify-
(i) On which days of the week and during which hours of the day pickup and delivery services may be required;
(ii) The maximum time allowable to the contractor for accomplishing delivery under regular or priority service; and
(iii) How much advance notice the contractor will be given for regular pickup services and, if applicable, priority pickup services.
Quick answers
What is FAR 47.207-2?
FAR 47.207-2 is a subsection of the Federal Acquisition Regulation, titled "Duration of contract and time of performance".
Are changes to FAR 47.207-2 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract