FAR 44.202-2 Considerations

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 44.202-2
Type
Subsection
Last amended
83 FR 48691 Effective Oct 26, 2018
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) The contracting officer responsible for consent must, at a minimum, review the request and supporting data and consider the following:

(1) Is the decision to subcontract consistent with the contractor’s approved make-or-buy program, if any (see 15.407-2)?

(2) Is the subcontract for special test equipment, equipment or real property that are available from Government sources?

(3) Is the selection of the particular supplies, equipment, or services technically justified?

(4) Has the contractor complied with the prime contract requirements regarding-

(i) Small business subcontracting, including, if applicable, its plan for subcontracting with small, veteran-owned, service-disabled veteran-owned, HUBZone, small disadvantaged and women-owned small business concerns (see part 19); and

(ii) Purchase from nonprofit agencies designated by the Committee for Purchase From People Who Are Blind or Severely Disabled 41 U.S.C.8504 (see part 8)?

(5) Was adequate price competition obtained or its absence properly justified?

(6) Did the contractor adequately assess and dispose of subcontractors’ alternate proposals, if offered?

(7) Does the contractor have a sound basis for selecting and determining the responsibility of the particular subcontractor?

(8) Has the contractor performed adequate cost or price analysis or price comparisons and obtained certified cost or pricing data and data other than certified cost or pricing data?

(9) Is the proposed subcontract type appropriate for the risks involved and consistent with current policy?

(10) Has adequate consideration been obtained for any proposed subcontract that will involve the use of Government-provided equipment and real property?

(11) Has the contractor adequately and reasonably translated prime contract technical requirements into subcontract requirements?

(12) Does the prime contractor comply with applicable cost accounting standards for awarding the subcontract?

(13) Is the proposed subcontractor listed as excluded in the System for Award Management (see subpart 9.4)?

(b) Particularly careful and thorough consideration under paragraph (a) of this section is necessary when-

(1) The prime contractor’s purchasing system or performance is inadequate;

(2) Close working relationships or ownership affiliations between the prime and subcontractor may preclude free competition or result in higher prices;

(3) Subcontracts are proposed for award on a non-competitive basis, at prices that appear unreasonable, or at prices higher than those offered to the Government in comparable circumstances; or

(4) Subcontracts are proposed on a cost-reimbursement, time-and-materials, or labor-hour basis.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation: System for Award Management Registration 83 FR 48691 · FAC 2005-101
Federal Acquisition Regulation; Positive Law Codification of Title 41 79 FR 24192 · FAC 2005-73
Federal Acquisition Regulation; System for Award Management Name Change, Phase 1 Implementation 78 FR 37676 · FAC 2005-67
Federal Acquisition Regulation; Definition of Cost or Pricing Data 75 FR 53135 · FAC 2005-45
Federal Acquisition Regulation; FAR Case 2007-015, Administrative Changes to the FPI Blanket Waiver and the JWOD Program Name 73 FR 53994 · FAC 2005-27
Federal Acquisition Regulation; FAR Case 2004-025, Government Property 72 FR 27364 · FAC 2005-17
Federal Acquisition Regulation; Excluded Parties List System Enhancement 69 FR 76347 · FAC 2001-26
Federal Acquisition Regulation; Javits-Wagner-O'Day Act Subcontract Preference Under Service Contracts 66 FR 65367 · FAC 2001-02

Sections cited

Quick answers

What is FAR 44.202-2?

FAR 44.202-2 is a subsection of the Federal Acquisition Regulation, titled "Considerations".

When was FAR 44.202-2 last changed?

The most recent final rule on record is "Federal Acquisition Regulation: System for Award Management Registration" (83 FR 48691), published Sep 26, 2018 and effective Oct 26, 2018.

Are changes to FAR 44.202-2 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract