FAR 4.804-1 Closeout by the office administering the contract

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 4.804-1
Type
Subsection
Last amended
84 FR 19839 Effective May 6, 2019
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) Except as provided in paragraph (c) of this section, time standards for closing out contract files are as follows:

(1) Files for contracts using simplified acquisition procedures should be considered closed when the contracting officer receives evidence of receipt of property and final payment, unless otherwise specified by agency regulations.

(2) Files for firm-fixed-price contracts, other than those using simplified acquisition procedures, should be closed within 6 months after the date on which the contracting officer receives evidence of physical completion.

(3) Files for contracts requiring settlement of indirect cost rates should be closed within 36 months of the month in which the contracting officer receives evidence of physical completion.

(4) Files for all other contracts should be closed within 20 months of the month in which the contracting officer receives evidence of physical completion.

(b) When closing out the contract files at 4.804-1(a)(2), (3), and (4), the contracting officer shall use the closeout procedures at 4.804-5. However, these closeout actions may be modified to reflect the extent of administration that has been performed. Quick closeout procedures (see 42.708) should be used, when appropriate, to reduce administrative costs and to enable deobligation of excess funds.

(c) A contract file shall not be closed if-

(1) The contract is in litigation or under appeal; or

(2) In the case of a termination, all termination actions have not been completed.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Technical Amendments 84 FR 19839 · FAC 2019-02

Sections cited

Quick answers

What is FAR 4.804-1?

FAR 4.804-1 is a subsection of the Federal Acquisition Regulation, titled "Closeout by the office administering the contract".

When was FAR 4.804-1 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Technical Amendments" (84 FR 19839), published May 6, 2019 and effective May 6, 2019.

Are changes to FAR 4.804-1 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract