FAR 39.103 Modular contracting
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 39.103
- Type
- Section
- Last amended
- 79 FR 24192 Effective May 29, 2014
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a) This section implements 41 U.S.C. 2308. Modular contracting is intended to reduce program risk and to incentivize contractor performance while meeting the Government’s need for timely access to rapidly changing technology. Consistent with the agency’s information technology architecture, agencies should, to the maximum extent practicable, use modular contracting to acquire major systems (see 2.101) of information technology. Agencies may also use modular contracting to acquire non-major systems of information technology.
(b) When using modular contracting, an acquisition of a system of information technology may be divided into several smaller acquisition increments that-
(1) Are easier to manage individually than would be possible in one comprehensive acquisition;
(2) Address complex information technology objectives incrementally in order to enhance the likelihood of achieving workable systems or solutions for attainment of those objectives;
(3) Provide for delivery, implementation, and testing of workable systems or solutions in discrete increments, each of which comprises a system or solution that is not dependent on any subsequent increment in order to perform its principal functions;
(4) Provide an opportunity for subsequent increments to take advantage of any evolution in technology or needs that occur during implementation and use of the earlier increments; and
(5) Reduce risk of potential adverse consequences on the overall project by isolating and avoiding custom-designed components of the system.
(c) The characteristics of an increment may vary depending upon the type of information technology being acquired and the nature of the system being developed. The following factors may be considered:
(1) To promote compatibility, the information technology acquired through modular contracting for each increment should comply with common or commercially acceptable information technology standards when available and appropriate, and shall conform to the agency’s master information technology architecture.
(2) The performance requirements of each increment should be consistent with the performance requirements of the completed, overall system within which the information technology will function and should address interface requirements with succeeding increments.
(d) For each increment, contracting officers shall choose an appropriate contracting technique that facilitates the acquisition of subsequent increments. Pursuant to parts 16 and 17 of the Federal Acquisition Regulation, contracting officers shall select the contract type and method appropriate to the circumstances (e.g., indefinite delivery, indefinite quantity contracts, single contract with options, successive contracts, multiple awards, task order contracts). Contract(s) shall be structured to ensure that the Government is not required to procure additional increments.
(e) To avoid obsolescence, a modular contract for information technology should, to the maximum extent practicable, be awarded within 180 days after the date on which the solicitation is issued. If award cannot be made within 180 days, agencies should consider cancellation of the solicitation in accordance with 14.209 or 15.206(e). To the maximum extent practicable, deliveries under the contract should be scheduled to occur within 18 months after issuance of the solicitation.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Positive Law Codification of Title 41 |
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53 | Closed Jul 23, 2026No final rule found |
Sections cited
- FAR 2.101 Definitions
- FAR Part 16 Types of Contracts
- FAR Part 17 Special Contracting Methods
- FAR 14.209 Cancellation of invitations before opening
- FAR 15.206(e) Amending the solicitation
Quick answers
What is FAR 39.103?
FAR 39.103 is a section of the Federal Acquisition Regulation, titled "Modular contracting".
When was FAR 39.103 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Positive Law Codification of Title 41" (79 FR 24192), published Apr 29, 2014 and effective May 29, 2014.
Are changes to FAR 39.103 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract