FAR 32.501-1 Customary progress payment rates

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 32.501-1
Type
Subsection
Last amended
87 FR 73894 Effective Dec 30, 2022
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) The customary progress payment rate is 80 percent, applicable to the total costs of performing the contract. The customary rate for contracts with small business concerns is 85 percent.

(b) The contracting officer must-

(1) Consider any rate higher than those permitted in paragraph (a) of this section an unusual progress payment; and

(2) Not include a higher rate in a contract unless advance agency approval is obtained as prescribed in 32.501-2.

(c) When advance payments and progress payments are authorized under the same contract, the contracting officer must not authorize a progress payment rate higher than the customary rate.

(d) In accordance with 10 U.S.C. 3804(b) and 41 U.S.C. 4504(b), the limit for progress payments is 80 percent on work accomplished under undefinitized contract actions. The contracting officer must not authorize a higher rate under unusual progress payments or other customary progress payments for the undefinitized actions.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation: Update to Title 10 Citations 87 FR 73894 · FAC 2023-01
Federal Acquisition Regulation; Positive Law Codification of Title 41 79 FR 24192 · FAC 2005-73
Federal Acquisition Regulation; Progress Payments and Related Financing Policies 65 FR 16276 · FAC 97-16

Sections cited

Quick answers

What is FAR 32.501-1?

FAR 32.501-1 is a subsection of the Federal Acquisition Regulation, titled "Customary progress payment rates".

When was FAR 32.501-1 last changed?

The most recent final rule on record is "Federal Acquisition Regulation: Update to Title 10 Citations" (87 FR 73894), published Dec 1, 2022 and effective Dec 30, 2022.

Are changes to FAR 32.501-1 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract