FAR 31.205-17 Idle facilities and idle capacity costs
Subsection Federal Acquisition Regulation
Facts
- Citation
- FAR 31.205-17
- Type
- Subsection
- Last amended
- 66 FR 2117 Effective Mar 12, 2001
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
(a) Definitions. As used in this subsection-
Costs of idle facilities or idle capacity means costs such as maintenance, repair, housing, rent, and other related costs; e.g., property taxes, insurance, and depreciation.
Facilities means plant or any portion thereof (including land integral to the operation), equipment, individually or collectively, or any other tangible capital asset, wherever located, and whether owned or leased by the contractor.
Idle capacity means the unused capacity of partially used facilities. It is the difference between that which a facility could achieve under 100 percent operating time on a one-shift basis, less operating interruptions resulting from time lost for repairs, setups, unsatisfactory materials, and other normal delays, and the extent to which the facility was actually used to meet demands during the accounting period. A multiple-shift basis may be used in the calculation instead of a one-shift basis if it can be shown that this amount of usage could normally be expected for the type of facility involved.
Idle facilities means completely unused facilities that are excess to the contractor’s current needs.
(b) The costs of idle facilities are unallowable unless the facilities-
(1) Are necessary to meet fluctuations in workload; or
(2) Were necessary when acquired and are now idle because of changes in requirements, production economies, reorganization, termination, or other causes which could not have been reasonably foreseen. (Costs of idle facilities are allowable for a reasonable period, ordinarily not to exceed 1 year, depending upon the initiative taken to use, lease, or dispose of the idle facilities (but see 31.205-42)).
(c) Costs of idle capacity are costs of doing business and are a factor in the normal fluctuations of usage or overhead rates from period to period. Such costs are allowable provided the capacity is necessary or was originally reasonable and is not subject to reduction or elimination by subletting, renting, or sale, in accordance with sound business, economics, or security practices. Widespread idle capacity throughout an entire plant or among a group of assets having substantially the same function may be idle facilities.
(d) Any costs to be paid directly by the Government for idle facilities or idle capacity reserved for defense mobilization production shall be the subject of a separate agreement.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Definitions |
Sections cited
- FAR 31.205-42 Termination costs
Terms defined
- Costs of idle facilities or idle capacity
- Facilities
- Idle capacity
- Idle facilities
Quick answers
What is FAR 31.205-17?
FAR 31.205-17 is a subsection of the Federal Acquisition Regulation, titled "Idle facilities and idle capacity costs".
When was FAR 31.205-17 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Definitions" (66 FR 2117), published Jan 10, 2001 and effective Mar 12, 2001.
Are changes to FAR 31.205-17 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract