FAR 31.202 Direct costs

Section Federal Acquisition Regulation

Facts

Citation
FAR 31.202
Type
Section
Last amended
69 FR 17764 Effective May 5, 2004
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) No final cost objective shall have allocated to it as a direct cost any cost, if other costs incurred for the same purpose in like circumstances have been included in any indirect cost pool to be allocated to that or any other final cost objective. Direct costs of the contract shall be charged directly to the contract. All costs specifically identified with other final cost objectives of the contractor are direct costs of those cost objectives and are not to be charged to the contract directly or indirectly.

(b) For reasons of practicality, the contractor may treat any direct cost of a minor dollar amount as an indirect cost if the accounting treatment-

(1) Is consistently applied to all final cost objectives; and

(2) Produces substantially the same results as treating the cost as a direct cost.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; General Provisions of the Cost Principles 69 FR 17764 · FAC 2001-22

Quick answers

What is FAR 31.202?

FAR 31.202 is a section of the Federal Acquisition Regulation, titled "Direct costs".

When was FAR 31.202 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; General Provisions of the Cost Principles" (69 FR 17764), published Apr 5, 2004 and effective May 5, 2004.

Are changes to FAR 31.202 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract