FAR 3.104-7 Violations or possible violations

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 3.104-7
Type
Subsection
Last amended
90 FR 507 Effective Jan 17, 2025
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) A contracting officer who receives or obtains information of a violation or possible violation of 41 U.S.C. 2102, 2103, or 2104 (see 3.104-3) must determine if the reported violation or possible violation has any impact on the pending award or selection of the contractor.

(1) If the contracting officer concludes that there is no impact on the procurement, the contracting officer must forward the information concerning the violation or possible violation and documentation supporting a determination that there is no impact on the procurement to an individual designated in accordance with agency procedures.

(i) If that individual concurs, the contracting officer may proceed with the procurement.

(ii) If that individual does not concur, the individual must promptly forward the information and documentation to the HCA and advise the contracting officer to withhold award.

(2) If the contracting officer concludes that the violation or possible violation impacts the procurement, the contracting officer must promptly forward the information to the HCA.

(b) The HCA must review all information available and, in accordance with agency procedures, take appropriate action, such as—

(1) Advise the contracting officer to continue with the procurement;

(2) Begin an investigation;

(3) Refer the information disclosed to appropriate criminal investigative agencies;

(4) Conclude that a violation occurred; or

(5) Recommend that the agency head determine that the contractor, or someone acting for the contractor, has engaged in conduct constituting an offense punishable under 41 U.S.C. 2105, for the purpose of voiding or rescinding the contract.

(c) Before concluding that an offeror, contractor, or person has violated 41 U.S.C. chapter 21, the HCA may consider that the interests of the Government are best served by requesting information from appropriate parties regarding the violation or possible violation.

(d) If the HCA concludes that 41 U.S.C. chapter 21 has been violated, the HCA may direct the contracting officer to-

(1) If a contract has not been awarded–

(i) Cancel the procurement;

(ii) Disqualify an offeror; or

(iii) Take any other appropriate actions in the interests of the Government.

(2) If a contract has been awarded-

(i) Effect appropriate contractual remedies, including profit recapture under the clause at 52.203-10, Price or Fee Adjustment for Illegal or Improper Activity, or, if the contract has been rescinded under paragraph (d)(2)(ii) of this subsection, recovery of the amount expended under the contract;

(ii) Void or rescind the contract with respect to which–

(A) The contractor or someone acting for the contractor has been convicted for an offense where the conduct constitutes a violation of 41 U.S.C. 2102 for the purpose of either-

(1) Exchanging the information covered by the subsections for anything of value; or

(2) Obtaining or giving anyone a competitive advantage in the award of a Federal agency procurement contract; or

(B) The agency head has determined, based upon a preponderance of the evidence, that the contractor or someone acting for the contractor has engaged in conduct constituting an offense punishable under 41 U.S.C. 2105(a); or

(iii) Take any other appropriate actions in the best interests of the Government.

(3) Refer the matter to the agency suspending and debarring official.

(e) The HCA should recommend or direct an administrative or contractual remedy commensurate with the severity and effect of the violation.

(f) If the HCA determines that urgent and compelling circumstances justify an award, or award is otherwise in the interests of the Government, the HCA, in accordance with agency procedures, may authorize the contracting officer to award the contract or execute the contract modification after notifying the agency head.

(g) The HCA may delegate his or her authority under this subsection to an individual at least one organizational level above the contracting officer and of General Officer, Flag, Senior Executive Service, or equivalent rank.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment 90 FR 507 · FAC 2025-03
Federal Acquisition Regulation; Positive Law Codification of Title 41 79 FR 24192 · FAC 2005-73
Federal Acquisition Regulation; Procurement Integrity Rewrite 67 FR 13057 · FAC 2001-06

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 91 FR 37698 · FAR Case 2026-007, Docket No. FAR-2026-0007, Sequence No. 1 Closed Jul 23, 2026No final rule found

Sections cited

  • FAR 3.104-3 Statutory and related prohibitions, restrictions, and requirements
  • FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity

Quick answers

What is FAR 3.104-7?

FAR 3.104-7 is a subsection of the Federal Acquisition Regulation, titled "Violations or possible violations".

When was FAR 3.104-7 last changed?

The most recent final rule on record is "Federal Acquisition Regulation: Improving Consistency Between Procurement and Nonprocurement Procedures on Suspension and Debarment" (90 FR 507), published Jan 3, 2025 and effective Jan 17, 2025.

Are changes to FAR 3.104-7 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract