FAR 22.302 Liquidated damages and overtime pay
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 22.302
- Type
- Section
- Last amended
- 83 FR 19148 Effective May 31, 2018
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a) When an overtime computation discloses underpayments, the responsible contractor or subcontractor must pay the affected employee any unpaid wages and pay liquidated damages to the Government. The contracting officer must assess liquidated damages at the rate specified at 29 CFR 5.5(b)(2) per affected employee for each calendar day on which the employer required or permitted the employee to work in excess of the standard workweek of 40 hours without paying overtime wages required by the statute. In accordance with the Federal Civil Penalties Inflation Adjustment Act of 1990 (28 U.S.C. 2461 Note), the Department of Labor adjusts this civil monetary penalty for inflation no later than January 15 each year.
(b) If the contractor or subcontractor fails or refuses to comply with overtime pay requirements of the statute and the funds withheld by Federal agencies for labor standards violations do not cover the unpaid wages due laborers and mechanics and the liquidated damages due the Government, make payments in the following order—
(1) Pay laborers and mechanics the wages they are owed (or prorate available funds if they do not cover the entire amount owed); and
(2) Pay liquidated damages.
(c) If the head of an agency finds that the administratively determined liquidated damages due under paragraph (a) of this section are incorrect, or that the contractor or subcontractor inadvertently violated the statute despite the exercise of due care, the agency head may-
(1) Reduce the amount of liquidated damages assessed for liquidated damages of $500 or less;
(2) Release the contractor or subcontractor from the liability for liquidated damages of $500 or less; or
(3) Recommend that the Secretary of Labor reduce or waive liquidated damages over $500.
(d) After the contracting officer determines the liquidated damages and the contractor makes appropriate payments, disburse any remaining assessments in accordance with agency procedures.
Federal Register history
Sections cited
- FAR Subpart 5.5(b)(2) Paid Advertisements
Quick answers
What is FAR 22.302?
FAR 22.302 is a section of the Federal Acquisition Regulation, titled "Liquidated damages and overtime pay".
When was FAR 22.302 last changed?
The most recent final rule on record is "Federal Acquisition Regulation: Liquidated Damages Rate Adjustment" (83 FR 19148), published May 1, 2018 and effective May 31, 2018.
Are changes to FAR 22.302 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract