FAR 22.101-4 Removal of items from contractors’ facilities affected by work stoppages

Subsection Federal Acquisition Regulation

Facts

Citation
FAR 22.101-4
Type
Subsection
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) Items shall be removed from contractors’ facilities affected by work stoppages in accordance with agency procedures. Agency procedures should allow for the following:

(1) Determine whether removal of items is in the Government’s interest. Normally the determining factor is the critical needs of an agency program.

(2) Attempt to arrange with the contractor and the union representative involved their approval of the shipment of urgently required items.

(3) Obtain appropriate approvals from within the agency.

(4) Determine who will remove the items from the plant(s) involved.

(b) Avoid the use or appearance of force and prevent incidents that might detrimentally affect labor-management relations.

(c) When two or more agencies’ requirements are or may become involved in the removal of items, the contract administration office shall ensure that the necessary coordination is accomplished.

Quick answers

What is FAR 22.101-4?

FAR 22.101-4 is a subsection of the Federal Acquisition Regulation, titled "Removal of items from contractors’ facilities affected by work stoppages".

Are changes to FAR 22.101-4 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract