FAR 16.603-2 Application
Subsection Federal Acquisition Regulation
Facts
- Citation
- FAR 16.603-2
- Type
- Subsection
- Last amended
- 75 FR 53135 Effective Oct 1, 2010
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
(a) A letter contract may be used when (1) the Government’s interests demand that the contractor be given a binding commitment so that work can start immediately and (2) negotiating a definitive contract is not possible in sufficient time to meet the requirement. However, a letter contract should be as complete and definite as feasible under the circumstances.
(b) When a letter contract award is based on price competition, the contracting officer shall include an overall price ceiling in the letter contract.
(c) Each letter contract shall, as required by the clause at 52.216-25, Contract Definitization, contain a negotiated definitization schedule including (1) dates for submission of the contractor's price proposal, required certified cost or pricing data and data other than certified cost or pricing data; and, if required, make-or-buy and subcontracting plans, (2) a date for the start of negotiations, and (3) a target date for definitization, which shall be the earliest practicable date for definitization. The schedule will provide for definitization of the contract within 180 days after the date of the letter contract or before completion of 40 percent of the work to be performed, whichever occurs first. However, the contracting officer may, in extreme cases and according to agency procedures, authorize an additional period. If, after exhausting all reasonable efforts, the contracting officer and the contractor cannot negotiate a definitive contract because of failure to reach agreement as to price or fee, the clause at 52.216-25 requires the contractor to proceed with the work and provides that the contracting officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31, subject to appeal as provided in the Disputes clause.
(d) The maximum liability of the Government inserted in the clause at 52.216-24, Limitation of Government Liability, shall be the estimated amount necessary to cover the contractor’s requirements for funds before definitization. However, it shall not exceed 50 percent of the estimated cost of the definitive contract unless approved in advance by the official that authorized the letter contract.
(e) The contracting officer shall assign a priority rating to the letter contract if it is appropriate under 11.604.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Definition of Cost or Pricing Data |
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 | Closed Oct 19, 2026No final rule found |
Sections cited
- FAR 52.216-25 Contract Definitization
- FAR Subpart 15.4 Contract Pricing
- FAR Part 31 Contract Cost Principles and Procedures
- FAR 52.216-24 Limitation of Government Liability
- FAR 11.604 Solicitation provision and contract clause
Quick answers
What is FAR 16.603-2?
FAR 16.603-2 is a subsection of the Federal Acquisition Regulation, titled "Application".
When was FAR 16.603-2 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Definition of Cost or Pricing Data" (75 FR 53135), published Aug 30, 2010 and effective Oct 1, 2010.
Are changes to FAR 16.603-2 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract