(a)

(1) The contracting officer shall insert the clause at 52.216-7, Allowable Cost and Payment, in solicitations and contracts when a cost-reimbursement contract or a time-and-materials contract (other than a contract for a commercial product or commercial service) is contemplated. If the contract is a time-and-materials contract, the clause at 52.216-7 applies in conjunction with the clause at 52.232-7), but only to the portion of the contract that provides for reimbursement of materials (as defined in the clause at 52.232-7) at actual cost. Further, the clause at 52.216-7 does not apply to labor-hour contracts.

(2) If the contract is a construction contract and contains the clause at 52.232-27, Prompt Payment for Construction Contracts, the contracting officer shall use the clause at 52.216-7 with its Alternate I.

(3) If the contract is with an educational institution, the contracting officer shall use the clause at 52.216-7 with its Alternate II.

(4) If the contract is with a State or local government, the contracting officer shall use the clause at 52.216-7 with its Alternate III.

(5) If the contract is with a nonprofit organization other than an educational institution, a State or local government, or a nonprofit organization exempted under the OMB Uniform Guidance at 2 CFR part 200, appendix VIII, the contracting officer shall use the clause at 52.216-7 with its Alternate IV.

(b) The contracting officer shall insert the clause at 52.216-8, Fixed Fee, in solicitations and contracts when a cost-plus-fixed-fee contract (other than a construction contract) is contemplated.

(c) The contracting officer shall insert the clause at 52.216-9, Fixed-Fee-Construction, in solicitations and contracts when a cost-plus-fixed-fee construction contract is contemplated.

(d) The contracting officer shall insert the clause at 52.216-10, Incentive Fee, in solicitations and contracts when a cost-plus-incentive-fee contract is contemplated.

(e)

(1) The contracting officer shall insert the clause at 52.216-11, Cost Contract-No Fee, in solicitations and contracts when a cost-reimbursement contract is contemplated that provides no fee and is not a cost-sharing contract.

(2) If a cost-reimbursement research and development contract with an educational institution or a nonprofit organization that provides no fee or other payment above cost and is not a cost-sharing contract is contemplated, and if the contracting officer determines that withholding of a portion of allowable costs is not required, the contracting officer shall use the clause with its Alternate I.

(f)

(1) The contracting officer shall insert the clause at 52.216-12, Cost-Sharing Contract-No Fee, in solicitations and contracts when a cost-sharing contract is contemplated.

(2) If a cost-sharing research and development contract with an educational institution or a nonprofit organization is contemplated, and if the contracting officer determines that withholding of a portion of allowable costs is not required, the contracting officer shall use the clause with its Alternate I.

(g) The contracting officer shall insert the clause at 52.216-15, Predetermined Indirect Cost Rates, in solicitations and contracts when a cost-reimbursement research and development contract with an educational institution (see 42.705-3(b)) is contemplated and predetermined indirect cost rates are to be used.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation: Revision of Definition of “Commercial Item” 86 FR 61017 · FAC 2022-01
Federal Acquisition Regulation; OMB Circular Citation Update 81 FR 45852 · FAC 2005-89
Federal Acquisition Regulation; Payments Under Time-and-Materials and Labor-Hour Contracts 77 FR 44059 · FAC 2005-60
Federal Acquisition Regulation; FAR Case 2004-025, Government Property 72 FR 27364 · FAC 2005-17
Federal Acquisition Regulation; FAR Case 2004-015, Payments Under Time-and-Materials and Labor-Hour Contracts 71 FR 74656 · FAC 2005-15

Sections cited

Quick answers

What is FAR 16.307?

FAR 16.307 is a section of the Federal Acquisition Regulation, titled "Contract clauses".

When was FAR 16.307 last changed?

The most recent final rule on record is "Federal Acquisition Regulation: Revision of Definition of “Commercial Item”" (86 FR 61017), published Nov 4, 2021 and effective Dec 6, 2021.

Are changes to FAR 16.307 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract