Text
A fixed-price contract with economic price adjustment may be used when (i) there is serious doubt concerning the stability of market or labor conditions that will exist during an extended period of contract performance, and (ii) contingencies that would otherwise be included in the contract price can be identified and covered separately in the contract. Price adjustments based on established prices should normally be restricted to industry-wide contingencies. Price adjustments based on labor and material costs should be limited to contingencies beyond the contractor’s control. For use of economic price adjustment in sealed bid contracts, see 14.408-4.
(a) In establishing the base level from which adjustment will be made, the contracting officer shall ensure that contingency allowances are not duplicated by inclusion in both the base price and the adjustment requested by the contractor under economic price adjustment clause.
(b) In contracts that do not require submission of certified cost or pricing data, the contracting officer shall obtain adequate data to establish the base level from which adjustment will be made and may require verification of data submitted.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Definition of Cost or Pricing Data |
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 16, 17, and 35 | Closed Oct 19, 2026No final rule found |
Sections cited
- FAR 14.408-4 Economic price adjustment
Quick answers
What is FAR 16.203-2?
FAR 16.203-2 is a subsection of the Federal Acquisition Regulation, titled "Application".
When was FAR 16.203-2 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Definition of Cost or Pricing Data" (75 FR 53135), published Aug 30, 2010 and effective Oct 1, 2010.
Are changes to FAR 16.203-2 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract