FAR 11.502 Procedures
Section Federal Acquisition Regulation
Facts
- Citation
- FAR 11.502
- Type
- Section
- Last amended
- 65 FR 46064 Effective Sep 25, 2000
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.
Text
(a) Include the applicable liquidated damages clause and liquidated damages rates in solicitations when the contract will contain liquidated damages provisions.
(b) Construction contracts with liquidated damages provisions must describe the rate(s) of liquidated damages assessed per day of delay. The rate(s) should include the estimated daily cost of Government inspection and superintendence. The rate(s) should also include an amount for other expected expenses associated with delayed completion such as-
(1) Renting substitute property; or
(2) Paying additional allowance for living quarters.
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Liquidated Damages |
Quick answers
What is FAR 11.502?
FAR 11.502 is a section of the Federal Acquisition Regulation, titled "Procedures".
When was FAR 11.502 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Liquidated Damages" (65 FR 46064), published Jul 26, 2000 and effective Sep 25, 2000.
Are changes to FAR 11.502 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract