DFARS 252.246-7002 Warranty of Construction (Germany)

Clause Defense Federal Acquisition Regulation Supplement Jun 1997 version

Facts

Citation
DFARS 252.246-7002
Type
Clause
Current version
June 1997
Prescribed in
DFARS 246.710(2)
Supplements
FAR Subpart 52.2 Text of Provisions and Clauses
Last amended
79 FR 17448 Effective Mar 28, 2014
Text as of
DFARS Change May 7, 2026
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 246.710 (2), use the following clause:

WARRANTY OF CONSTRUCTION (GERMANY) (JUN 1997)

(a) In addition to any other representations in this contract, the Contractor warrants, except as provided in paragraph (j) of this clause, that the work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for the period(s) specified in Section 13, VOB, Part B, commencing from the date of final acceptance of the work under this contract. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for the period(s) specified in Section 13, VOB, Part B, from the date the Government takes possession.

(c) The Contractor shall remedy, at the Contractor’s expense, any failure to conform or any defect. In addition, the Contractor shall remedy, at the Contractor’s expense, any damage to Government-owned or -controlled real or personal property when that damage is the result of—

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, or design furnished or workmanship performed.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable period of time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable period of time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall—

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government as directed by the Contracting Officer.

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.

(i) Unless a defect is caused by the Contractor’s negligence, or the negligence of a subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government or for the repair of any damage resulting from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government’s right under the Inspection clause of this contract, with respect to latent defects, gross mistakes, or fraud.

(End of clause)

Federal Register history

Final rule Published Effective
Defense Federal Acquisition Regulation Supplement: Clauses With Alternates-Quality Assurance (DFARS Case 2013-D004) 79 FR 17448 · 0750-AH95

Quick answers

What is DFARS 252.246-7002?

DFARS 252.246-7002 is a clause of the Defense Federal Acquisition Regulation Supplement, titled "Warranty of Construction (Germany)".

What is the current version of DFARS 252.246-7002?

The current version is dated June 1997.

Where is DFARS 252.246-7002 prescribed?

It is prescribed in DFARS 246.710(2), Contract clauses.

When was DFARS 252.246-7002 last changed?

The most recent final rule on record is "Defense Federal Acquisition Regulation Supplement: Clauses With Alternates-Quality Assurance (DFARS Case 2013-D004)" (79 FR 17448), published Mar 28, 2014 and effective Mar 28, 2014.

Are changes to DFARS 252.246-7002 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract