DFARS 252.236-7007 Additive or Deductive Items
Solicitation provision Defense Federal Acquisition Regulation Supplement Dec 1991 version
Facts
- Citation
- DFARS 252.236-7007
- Type
- Solicitation provision
- Current version
- December 1991
- Prescribed in
- DFARS 236.570(b)(5)
- Supplements
- FAR Subpart 52.2 Text of Provisions and Clauses
- Text as of
- DFARS Change May 7, 2026
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this solicitation provision.
Text
As prescribed in 236.570 (b)(5), use the following provision:
ADDITIVE OR DEDUCTIVE ITEMS (DEC 1991)
(a) The low offeror and the items to be awarded shall be determined as follows—
(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.
(2) The low offeror shall be the Offeror that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.
(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.
(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and
(ii) Add that next item if an award may be made that includes that item and is within the available funds.
(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—
(1) It is in the best interest of the Government;
(2) Funds are available at the time of award; and
(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.
(c) Example. The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.
(End of provision)
Quick answers
What is DFARS 252.236-7007?
DFARS 252.236-7007 is a solicitation provision of the Defense Federal Acquisition Regulation Supplement, titled "Additive or Deductive Items".
What is the current version of DFARS 252.236-7007?
The current version is dated December 1991.
Where is DFARS 252.236-7007 prescribed?
It is prescribed in DFARS 236.570(b)(5), Additional provisions and clauses.
Are changes to DFARS 252.236-7007 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract