DFARS 252.217-7003 Changes

Clause Defense Federal Acquisition Regulation Supplement Dec 1991 version

Facts

Citation
DFARS 252.217-7003
Type
Clause
Current version
December 1991
Prescribed in
DFARS 217.7104(a)
Supplements
FAR Subpart 52.2 Text of Provisions and Clauses
Last amended
75 FR 48278 Effective Aug 10, 2010
Text as of
DFARS Change May 7, 2026
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 217.7104 (a), use the following clause:

CHANGES (DEC 1991)

(a) The Contracting Officer may, at any time and without notice to the sureties, by written change order, make changes within the general scope of any job order issued under the Master Agreement in—

(1) Drawings, designs, plans, and specifications;

(2) Work itemized;

(3) Place of performance of the work;

(4) Time of commencement or completion of the work; and

(5) Any other requirement of the job order.

(b) If a change causes an increase or decrease in the cost of, or time required for, performance of the job order, whether or not changed by the order, the Contracting Officer shall make an equitable adjustment in the price or date of completion, or both, and shall modify the job order in writing.

(1) Within ten days after the Contractor receives notification of the change, the Contractor shall submit to the Contracting Officer a request for price adjustment, together with a written estimate of the increased cost.

(2) The Contracting Officer may grant an extension of this period if the Contractor requests it within the ten day period.

(3) If the circumstances justify it, the Contracting Officer may accept and grant a request for equitable adjustment at any later time prior to final payment under the job order, except that the Contractor may not receive profit on a payment under a late request.

(c) If the Contractor includes in its claim the cost of property made obsolete or excess as a result of a change, the Contracting Officer shall have the right to prescribe the manner of disposition of that property.

(d) Failure to agree to any adjustment shall be a dispute within the meaning of the Disputes clause.

(e) Nothing in this clause shall excuse the Contractor from proceeding with the job order as changed.

(End of clause)

Federal Register history

Final rule Published Effective
Defense Federal Acquisition Regulation Supplement; Excessive Pass-Through Charges 75 FR 48278 · DFARS Case 2006-D057

Quick answers

What is DFARS 252.217-7003?

DFARS 252.217-7003 is a clause of the Defense Federal Acquisition Regulation Supplement, titled "Changes".

What is the current version of DFARS 252.217-7003?

The current version is dated December 1991.

Where is DFARS 252.217-7003 prescribed?

It is prescribed in DFARS 217.7104(a), Contract clauses.

When was DFARS 252.217-7003 last changed?

The most recent final rule on record is "Defense Federal Acquisition Regulation Supplement; Excessive Pass-Through Charges" (75 FR 48278), published Aug 10, 2010 and effective Aug 10, 2010.

Are changes to DFARS 252.217-7003 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract