DFARS 249.501-70 Special termination costs
Subsection Defense Federal Acquisition Regulation Supplement
Facts
- Citation
- DFARS 249.501-70
- Type
- Subsection
- Supplements
- FAR 49.501 General
- Text as of
- DFARS Change May 7, 2026
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.
Text
(a) The clause at 252.249-7000 , Special Termination Costs, may be used in an incrementally funded contract when its use is approved by the agency head.
(b) The clause is authorized when—
(1) The contract term is two years or more;
(2) The contract is estimated to require—
(i) Total RDT&E financing in excess of $25 million; or
(ii) Total production investment in excess of $100 million; and
(3) Adequate funds are available to cover the contingent reserve liability for special termination costs.
(c) The contractor and the contracting officer must agree upon an amount that represents their best estimate of the total special termination costs to which the contractor would be entitled in the event of termination of the contract. Insert this amount in paragraph (c) of the clause.
(d)
(1) Consider substituting an alternate paragraph (c) for paragraph (c) of the basic clause when—
(i) The contract covers an unusually long performance period; or
(ii) The contractor's cost risk associated with contingent special termination costs is expected to fluctuate extensively over the period of the contract.
(2) The alternate paragraph (c) should provide for periodic negotiation and adjustment of the amount reserved for special termination costs. Occasions for periodic adjustment may include—
(i) The Government's incremental assignment of funds to the contract;
(ii) The time when certain performance milestones are accomplished by the contractor; or
(iii) Other specific time periods agreed upon by the contracting officer and the contractor.
Sections cited
- DFARS 252.249-7000 Special Termination Costs
Quick answers
What is DFARS 249.501-70?
DFARS 249.501-70 is a subsection of the Defense Federal Acquisition Regulation Supplement, titled "Special termination costs".
Are changes to DFARS 249.501-70 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract