Text

(a) *Criteria for conducting reviews.*Conduct an MMAS review when—

(1) A contractor has $40 million of qualifying sales to the Government during the contractor's preceding fiscal year; and

(2) The administrative contracting officer (ACO), with advice from the auditor, determines an MMAS review is needed based on a risk assessment of the contractor's past experience and current vulnerability.

(b) Qualifying sales. Qualifying sales are sales for which certified cost or pricing data were required under 10 U.S.C. 3702, as implemented in FAR 15.403, or that are contracts priced on other than a firm-fixed-price or fixed-price with economic price adjustment basis. Sales include prime contracts, subcontracts, and modifications to such contracts and subcontracts.

(c) Disposition of findings—

(1) Reporting of findings. The auditor or functional specialist shall document findings and recommendations in a report to the contracting officer. If the auditor or functional specialist identifies any material weakness, the report shall describe the weaknesses or deficiencies in sufficient detail to allow the contracting officer to understand the weaknesses or deficiencies.

(2) Initial determination.

(i) The contracting officer shall review findings and recommendations and, if there are no material weaknesses, shall promptly notify the contractor, in writing, that the contractor’s MMAS is acceptable and approved; or

(ii) If the contracting officer finds that there are one or more http://www.acq.osd.mil/dpap/dars/dfars/html/current/252242.htm#252.242-7004 material weaknesses due to the contractor’s failure to meet one or more of the MMAS system criteria in the clause at 252.242-7004, the contracting officer shall—

(A) Promptly make an initial written determination on any material weaknesses and notify the contractor, in writing, providing a description of each material weakness in sufficient detail to allow the contractor to understand the weakness or deficiency;

(B) Request the contractor to respond, in writing, to the initial determination within 30 days; and

(C) Promptly evaluate the contractor’s response to the initial determination in consultation with the auditor or functional specialist and make a final determination (see PGI 242.7203(c)(2)).

(3) Final determination.

(i) The ACO shall make a final determination and notify the contractor that—

(A) The contractor’s MMAS is acceptable and approved, and no deficiencies remain; or

(B) Material weaknesses remain. The notice shall identify any remaining material weaknesses and indicate the adequacy of any proposed or completed corrective action. The contracting officer shall—

(1) ) Request that the contractor, within 45 days of receipt of the final determination, either correct the weaknesses or submit an acceptable corrective action plan showing milestones and actions to eliminate the weaknesses;

(2) ) Disapprove the system in accordance with the clause at 252.242-7004; and

(3) ) Withhold payments in accordance with the clause at 252.242-7005 , Contractor Business Systems, if the clause is included in the contract.

(ii) Follow the procedures relating to monitoring a contractor’s corrective action and the correction of material weaknesses in PGI 242.7203 (c)(3) .

(d) System approval. The contracting officer shall promptly approve a previously disapproved MMAS and notify the contractor when the contracting officer determines that there are no remaining material weaknesses.

(e) Contracting officer notifications. The cognizant contracting officer shall promptly distribute copies of a determination to approve a system, disapprove a system and withhold payments, or approve a previously disapproved system and release withheld payments to the auditor; payment office; affected contracting officers at the buying activities; and cognizant contracting officers in contract administration activities.

Federal Register history

Sections cited

Quick answers

What is DFARS 242.7203?

DFARS 242.7203 is a section of the Defense Federal Acquisition Regulation Supplement, titled "Review procedures".

When was DFARS 242.7203 last changed?

The most recent final rule on record is "Defense Federal Acquisition Regulation Supplement: Definition of Material Weakness (DFARS Case 2021-D006)" (90 FR 5725), published Jan 17, 2025 and effective Jan 17, 2025.

Are changes to DFARS 242.7203 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract