DFARS 217.7404-3 Definitization schedule

Subsection Defense Federal Acquisition Regulation Supplement

Facts

Citation
DFARS 217.7404-3
Type
Subsection
Supplements
FAR Part 17 Special Contracting Methods
Last amended
88 FR 33835 Effective May 25, 2023
Text as of
DFARS Change May 7, 2026
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this subsection.

Text

(a) UCAs shall contain definitization schedules that provide for definitization by the earlier of—

(1) The date that is 180 days after the contractor submits a qualifying proposal. This date may not be extended beyond an additional 90 days without a written determination by the head of the contracting activity without power of redelegation, the commander of the combatant command concerned, or the Under Secretary of Defense for Acquisition and Sustainment that it is in the best interests of the military department or the defense agency, the combatant command, or the Department of Defense, respectively, to continue the action; or

(2) The date on which the amount of funds obligated under the contract action is equal to more than 50 percent of the not-to-exceed price.

(b)

(1) Submission of a qualifying proposal in accordance with the definitization schedule is a material element of the contract. If the contractor does not submit a qualifying proposal in accordance with the contract definitization schedule, notwithstanding FAR 52.216-26, Payments of Allowable Costs Before Definitization, the contracting officer may withhold an amount necessary to protect the interests of the Government, not to exceed 5 percent of all subsequent financing requests, or take other appropriate actions (e.g., documenting the noncompliance in the contractor’s past performance evaluation or terminating the contract for default).

(2) Contracting officers shall document in the contract file the justification for withholding or not withholding payments if the qualifying proposal was not submitted in accordance with the contract definitization schedule.

Federal Register history

Final rule Published Effective
Defense Federal Acquisition Regulation Supplement: Undefinitized Contract Actions (DFARS Case 2021-D003) 88 FR 33835 · Docket DARS-2022-0026
Defense Federal Acquisition Regulation Supplement: Undefinitized Contract Actions (DFARS Case 2018-D008) 84 FR 39204 · Docket DARS-2019-0004

Sections cited

  • FAR 52.216-26 Payments of Allowable Costs Before Definitization

Quick answers

What is DFARS 217.7404-3?

DFARS 217.7404-3 is a subsection of the Defense Federal Acquisition Regulation Supplement, titled "Definitization schedule".

When was DFARS 217.7404-3 last changed?

The most recent final rule on record is "Defense Federal Acquisition Regulation Supplement: Undefinitized Contract Actions (DFARS Case 2021-D003)" (88 FR 33835), published May 25, 2023 and effective May 25, 2023.

Are changes to DFARS 217.7404-3 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract