DFARS 217.172 Multiyear contracts for supplies

Section Defense Federal Acquisition Regulation Supplement

Facts

Citation
DFARS 217.172
Type
Section
Supplements
FAR Subpart 17.1 Multi-year Contracting
Last amended
90 FR 41483 Effective Oct 1, 2025
Text as of
DFARS Change May 7, 2026
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) This section applies to all multiyear contracts for supplies, including weapon systems and other multiyear acquisitions specifically authorized by law (10 U.S.C. 3501).

(b) The head of the agency may enter into a multiyear contract for supplies if, in addition to the conditions listed in FAR 17.105-1(b), the use of such a contract will promote the national security of the United States (10 U.S.C. 3501(a)(6)).

(c) Multiyear contracts in amounts exceeding $900 million must be specifically authorized by law in an act other than an appropriations act (10 U.S.C. 3501(i)(1)).

(d) The head of the agency may not initiate a multiyear procurement contract for any system (or component thereof) if the value of the multiyear contract would exceed $900 million unless authority for the contract is specifically provided in an appropriations act (10 U.S.C. 3501(l)(3)).

(1) The Secretary of Defense has submitted to Congress a budget request for full funding of units to be procured through the contract;

(2) In the case of a contract for procurement of aircraft, the budget request includes full funding of procurement funds for production beyond advance procurement activities of aircraft units to be produced in the fiscal year covered by the budget;

(3) Cancellation provisions in the contract do not include consideration of recurring manufacturing costs of the contractor associated with the production of unfunded units to be delivered under the contract;

(4) The contract provides that payments to the contractor under the contract shall not be made in advance of incurred costs on funded units; and

(5) The contract does not provide for a price adjustment based on a failure to award a follow-on contract (section 8010 of Division C, Title VIII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and similar sections in subsequent DoD appropriations acts).

(f)

(1) The head of the agency must not enter into or extend a multiyear contract that exceeds $900 million (when entered into or extended) until the Secretary of Defense identifies the contract and any extension in a report submitted to the congressional defense committees (10 U.S.C. 3501(l)(5)).

(2) In addition, for contracts equal to or greater than $900 million, the head of the contracting activity must determine that the conditions required by paragraphs (h)(2)(i) through (vii) of this section will be met by such contract, in accordance with the Secretary’s certification and determination required by paragraph (h)(2) of this section.

(g) The head of the agency may enter into a multiyear contract for—

(1) A weapon system and associated items, services, and logistics support for a weapon system (10 U.S.C.3501(h)(1)); and

(2) Advance procurement of components, parts, and materials necessary to manufacture a weapon system, including advance procurement to achieve economic lot purchases or more efficient production rates (see 217.172 (h)(3) and (4) of this section regarding economic order quantity procurements) (10 U.S.C. 3501(h)(2)). Before initiating an advance procurement, the contracting officer must verify that it is consistent with DoD policy (e.g., the full funding policy in Volume 2A, chapter 1, of DoD 7000.14-R, Financial Management Regulation).

(h) The head of the agency shall ensure that the following conditions are satisfied before awarding a multiyear contract for a defense acquisition program that has been specifically authorized by law to be carried out using multiyear contract authority:

(1) The multiyear exhibits required by DoD 7000.14-R, Financial Management Regulation, are included in the agency’s budget estimate submission and the President’s budget request.

(2) The Secretary of Defense certifies to Congress in writing, by no later than30 days before entry into such contracts, that each of the conditions in paragraphs (h)(2)(i) through (vii) of this section is satisfied (10 U.S.C.3501(i)(3).

(i) The Secretary has determined that each of the requirements in FAR 17.105-1, paragraphs (b)(1) through (b)(5), will be met by such contract and has provided the basis for such determination to the congressional defense committees (10 U.S.C. 3501(i)(3)(A)).

(ii) The Secretary’s determination under paragraph (h)(2)(i) of this section was made after the completion of a cost analysis performed by the Defense Cost and Resource Center of the Department of Defense and such analysis supports the findings (10 U.S.C. 3501(i)(3)(B)).

(iii) The system being acquired pursuant to such contract has not been determined to have experienced cost growth in excess of the critical cost growth threshold pursuant to 10 U.S.C 4371(a)(3) within 5 years prior to the date the Secretary anticipates such contract (or a contract for advance procurement entered into consistent with the authorization for such contract) will be awarded (10 U.S.C. 3501(i)(3)(C)).

(iv) A sufficient number of end items of the system being acquired under such contract have been delivered at or within the most current estimates of the program acquisition unit cost or procurement unit cost for such system to determine that current estimates of such unit costs are realistic (10 U.S.C.3501(i)(3)(D)).

(v) Sufficient funds will be available in the fiscal year in which the contract is to be awarded to perform the contract, and the future-years defense program for such fiscal year will include the funding required to execute the program without cancellation (10 U.S.C. 2306b(i)(3)(E)).

(vi) The contract is a fixed price type contract (10 U.S.C. 3501(i)(3)(F)).

(vii) The proposed multiyear contract provides for production at not less than minimum economic rates, given the existing tooling and facilities (10 U.S.C. 3501(i)(3)(G)). The head of the agency shall submit to OUSD(C)(P/B) information supporting the agency’s determination that this requirement has been met.

(viii) The head of the agency shall submit information supporting this certification to OUSD(C)(P/B) for transmission to Congress through the Secretary of Defense.

(A) The head of the agency shall, as part of this certification, give written notification to the congressional defense committees of—

(1) The cancellation ceiling amounts planned for each program year in the proposed multiyear contract, together with the reasons for the amounts planned;

(2) The extent to which costs of contract cancellation are not included in the budget for the contract; and

(3) A financial risk assessment of not including the budgeting for costs of contract cancellation (10 U.S.C. 3501(g)); and

(B) The head of the agency shall provide copies of the notification to the Office of Management and Budget at least 14 days before contract award.

(3) The contract is for the procurement of a complete and usable end item (10 U.S.C. 3501(i)(5)(A)).

(4) Funds appropriated for any fiscal year for advance procurement are obligated only for the procurement of those long-lead items that are necessary in order to meet a planned delivery schedule for complete major end items that are programmed under the contract to be acquired with funds appropriated for a subsequent fiscal year (including an economic order quantity of such long-lead items when authorized by law (10 U.S.C. 3501(i)(5)(B)).

(5) The Secretary may make the certification under paragraph (h)(2) of this section notwithstanding the fact that one or more of the conditions of such certification are not met if the Secretary determines that, due to exceptional circumstances, proceeding with a multiyear contract under this section is in the best interest of the Department of Defense and the Secretary provides the basis for such determination with the certification (10 U.S.C. 3501(i)(6)).

(6) The Secretary of Defense may not delegate this authority to make the certification under paragraph (h)(2) of this section or the determination under paragraph (h)(5) of this section to an official below the level of the Under Secretary of Defense for Acquisition and Sustainment (10 U.S.C. 3501(i)(7)).

(7) All other requirements of law are met and there are no other statutory restrictions on using a multiyear contract for the specific system or component. One such restriction may be the achievement of specified cost savings. If the agency finds, after negotiations with the contractor(s), that the specified savings cannot be achieved, the head of the agency shall assess the savings that, nevertheless, could be achieved by using a multiyear contract. If the savings are substantial, the head of the agency may request relief from the law’s specific savings requirement (10 U.S.C. 3501(i)(4)). The request shall—

(i) Quantify the savings that can be achieved;

(ii) Explain any other benefits to the Government of using the multiyear contract;

(iii) Include details regarding the negotiated contract terms and conditions; and

(iv) Be submitted to OUSD(A&S)(DPCAP) for transmission to Congress via the Secretary of Defense and the President.

(i) The Secretary of Defense may instruct the head of the agency proposing a multiyear contract to include in that contract negotiated priced options for varying the quantities of end items to be procured over the life of the contract (10 U.S.C. 3501(j)).

(j) Any requests for increased funding or reprogramming for procurement of a major system under a multiyear contract shall be accompanied by an explanation of how the request for increased funding affects the determinations made by the Secretary of Defense under 217.172 (h)(2) (10 U.S.C. 3501(m)).

Federal Register history

Final rule Published Effective
Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002) 90 FR 41483 · Docket DARS-2024-0039
Defense Federal Acquisition Regulation Supplement; Technical Amendments 90 FR 5735 · Docket DARS-2024-0001
Defense Federal Acquisition Regulation Supplement; Technical Amendments 89 FR 60830 · Docket DARS-2024-0001
Defense Federal Acquisition Regulation Supplement: Reorganization of Defense Acquisition Statutes (DFARS Case 2022-D018) 87 FR 76988 · Docket DARS-2022-0031
Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2019-D036) 85 FR 61502 · Docket DARS-2020-0002
Defense Federal Acquisition Regulation Supplement: Multiyear Contract Requirements (DFARS Case 2015-D009) 81 FR 28730 · Docket DARS-2015-0067
Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2014-D025) 80 FR 36903 · 0750-AI43
Defense Federal Acquisition Regulation Supplement: Multiyear Contracts-Statutory References and Cancellation Ceiling Threshold (DFARS Case 2014-D019) 80 FR 29981 · 0750-AI37
Defense Federal Acquisition Regulation Supplement; Multiyear Contracting (DFARS Case 2009-D026) 76 FR 58152 · 0750-AG89
Defense Federal Acquisition Regulation Supplement; Additional Requirements Applicable to Multiyear Contracts 75 FR 54526 · DFARS Case 2008-D023
Defense Federal Acquisition Regulation Supplement; Additional Requirements Applicable to Multiyear Contracts (DFARS Case 2008-D023) 75 FR 9114
Defense Federal Acquisition Regulation Supplement; Multiyear Contracting 70 FR 24323 · DFARS Case 2004-D024
Defense Federal Acquisition Regulation Supplement; Multiyear Contracting Authority Revisions 68 FR 50474 · DFARS Case 2002-D041
Defense Federal Acquisition Regulation Supplement; Multiyear Contracting 66 FR 63336 · DFARS Case 2000-D303/304 Not on record
Show all 14

Quick answers

What is DFARS 217.172?

DFARS 217.172 is a section of the Defense Federal Acquisition Regulation Supplement, titled "Multiyear contracts for supplies".

When was DFARS 217.172 last changed?

The most recent final rule on record is "Defense Federal Acquisition Regulation Supplement: Inflation Adjustment of Acquisition-Related Thresholds (DFARS Case 2024-D002)" (90 FR 41483), published Aug 25, 2025 and effective Oct 1, 2025.

Are changes to DFARS 217.172 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search