About this opportunity
The City of Farmers Branch, Texas is soliciting sealed bids for Phase 3 of its Water & Wastewater System 2026 Capital Improvements Plan, with a pre-bid conference on December 8, 2026 and bids due December 17, 2026 at 2:00 p.m. at Farmers Branch City Hall, 13000 William Dodson Parkway.
The work includes approximately 4,213 linear feet of 8-inch PVC water line by open cut, 1,506 linear feet of 12-inch PVC water line by open cut, 1,097 linear feet of 10-inch line, 2,152 linear feet of 12-inch SDR 19 IPS sanitary sewer line by pipe bursting, 1,611 linear feet of 12-inch SDR 26 PVC sanitary sewer line by open cut, 26 five-foot diameter manholes, and approximately 4,171 square yards of 10-inch reinforced concrete pavement, along with all necessary appurtenances. Bidders must post bid security of 5% of the total bid by cashier's check, certified check, or bid bond. The successful bidder must furnish performance, payment, and maintenance bonds, each at 100% of the contract price, with the maintenance bond remaining in effect for two years from final acceptance. Within 24 hours after bid opening, bidders must complete the Contractor Information form. The qualified low bidder must electronically file Form 1295 (Certificate of Interested Parties) with the State Ethics Commission and submit the notarized copy with certificate number to the City within 72 hours of bid opening.
The City will select the low qualified bidder based on greatest advantage to the Owner, considering bid prices and the bidder's ability, standing, and reputation. The project is exempt from applicable state and local sales taxes under Texas Tax Code Section 151.311.
Contract documents are available electronically through Civcast (civcastusa.com) at no charge for viewing or downloading, and printed sets are available for a cost. Questions are due December 10, 2026 at 5:00 p.m. through Civcast, and addenda will be posted by December 14, 2026. The City anticipates awarding the contract by February 2, 2027. The contractor must commence work within 10 calendar days of written notice and substantially complete the project within 180 calendar days, with construction scheduled from February 2027 through August 2027.
Opportunity text
This project generally includes the construction of approximately 4,213 linear feet of 8-Inch PVC water line by open cut, 1,506 linear feet of 12-Inch PVC water line by open cut, 1,097 linear feet of 10-Inch, and 2,152 linear feet of 12-inch SDR 19 IPS sanitary sewer line by pipe bursting, 1,611 linear feet of 12-inch SDR 26 PVC sanitary sewer line by open cut, 26 - 5.0 foot diameter manholes, and approximately 4,171 square yards of 10-Inch Reinforced Concrete Pavement, along with all necessary appurtenances.
Files
| File | Type | Posted |
|---|---|---|
| 26-35 Water and Wastewater - Contract Documents and Specifications.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity