About this opportunity

The Municipal Authority of the City of Monongahela, Pennsylvania, solicited sealed bids under Contract No. 2026-01 for Wastewater Treatment Plant Outfall Channel Restoration, with bids due October 14, 2026 at 10:00 a.m. through PennBid. That deadline has passed, and the bid tabulation records three bids received. The work is subject to the Pennsylvania Prevailing Wage Act, with certified weekly payrolls from the contractor and all subcontractors submitted to project engineer Hatch Associates Consultants, Inc.

The scope is placing approximately 200 tons of rip-rap to stabilize the extended outfall channel after changes to the Monongahela River's normal pool. Addendum No. 1 revised the quantity from 205 tons. Bid items include mobilization and demobilization, clearing and grubbing, R5 and R6 stone, marine composite geogrid lining, Class 2 excavation, clean fill, erosion and sedimentation control, and grading and site restoration. The geogrid basis of design is BaseLok MCBX3030L biaxial geogrid or an owner-approved equivalent meeting all performance specifications. The contractor provides utilities and work facilities, hauls removed materials to Pennsylvania Department of Environmental Protection-approved sites, and manages outfall and river flow bypass under PADEP General Permit 4 and U.S. Army Corps of Engineers PASPGP-6 authorization. The contractor also obtains local permits, pays road bonding and City of Monongahela mercantile taxes, and keeps a project superintendent on-site whenever work is performed. Work is at the Municipal Authority's treatment facility near W. Main and 12th Street, Monongahela, Washington County.

Bid security is 10% of the bid amount, by certified check, cashier's check, or bid bond. The contractor must furnish a performance and maintenance bond and a labor and materialmen's bond, each equal to 100% of the contract price, plus a two-year warranty from final certificate of completion. Liquidated damages are $600 per day. Completion is due 150 consecutive calendar days from contract award, and the low responsive, responsible bidder who files the required surety bonds receives award. Bids were Hunt Valley Environmental, LLC at $105,000; Meadville Land Service, Inc. at $109,950; and Hogen's Heroes, Inc. dba J5 Construction at $134,000. Unit prices diverged sharply, with clearing and grubbing ranging from $4,085 to $89,300 across bidders. Bids remain valid 60 calendar days after closing.

The virtual pre-bid conference was scheduled for October 5, 2026 at 10:30 a.m. through Microsoft Teams, and Addendum No. 1 reports it was held. Questions closed October 8, 2026 at 12:00 p.m.

Opportunity text

The project consists of the installation of approximately 205 tons of rip-rap to stabilize and protect the extended Wastewater Treatment Plant outfall channel following the change in the normal pool of the Monongahela River.

Files

File Type Posted
2-Addendum 1.pdf PDF
1-2026-01 Issued 09.21.2026.pdf PDF
3-2026-01 BID TAB.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for State & Local Contractors