About this opportunity
The Board of Regents of the University of Minnesota is soliciting lump-sum proposals for construction services to remodel Pods K and L in Griggs Hall on the Duluth campus, with a mandatory pre-proposal meeting on November 11, 2026 at 1:00 p.m. Central Time and proposals due November 24, 2026 at 2:00 p.m. Proof of attendance at the pre-proposal meeting is pass/fail. The solicitation is listed under St. Louis County, Minnesota.
The University has voluntarily elected to comply with Minnesota Statutes Section 16C.285 responsible contractor minimum criteria. Respondents must submit a Responsible Contractor Certification of Compliance and First-Tier Subcontractor List with their proposals, and responsible contractor verification is pass/fail. Respondents must also demonstrate prevailing wage compliance and achieve a safety score of 5.0 or greater to be considered for award.
The scope includes one new air handling unit per pod, replacement of existing rooftop unit ventilators, revised toilet room layouts with new plumbing fixtures, piping, ventilation, and lighting, replacement of light fixtures, architectural finishes upgrades, and door and hardware replacements. Each lump-sum bid must include a $25,000 allowance for conduit removal within the slab, refundable if the work is not needed.
The total construction budget is $3.8 million in current dollars with no escalation. The selected respondent performs all work for a fixed lump sum that includes all costs, overhead, and profit. Substantial completion is required by July 30, 2027. The contract is the University's Construction Agreement OGC-SC900, incorporating AIA A201-2017 General Conditions as modified by the University on January 1, 2026, with no exceptions or deviations permitted.
Evaluation weights are team qualifications at 35 points, project cost at 30 points, project approach and work plan at 20 points, project schedule at 10 points, and safety at 5 points. Pass/fail requirements apply to the RFP cover page, responsible contractor verification, and proof of attendance at the mandatory pre-proposal meeting.
Questions are due November 17, 2026 at noon. The University plans to identify a potential selected respondent on December 3, 2026, with authorization to proceed anticipated for December 8, 2026.
Opportunity text
The scope of the Work for remodeling Pods K and L of the Griggs Hall dormitory will include: One new air handling unit installed for each pod. Replacement of existing rooftop unit ventilators. Revised toilet room layouts with new plumbing fixtures, piping, ventilation, and lighting. Replace existing light fixtures. Architectural finishes upgrades. Door and hardware replacements.
Files
| File | Type | Posted |
|---|---|---|
| RFP - Griggs Pods K_L.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity