Smoke and Fire Damper Inspection

Open State & local contract opportunity Posted

Solicitation number
SRC0000042419
State
Ohio
Responses due

Opportunity facts

Jurisdictions

Opportunity details come from ohiobuys.ohio.gov. Updated .

About this opportunity

Summit Behavioral Healthcare is soliciting bids for a 6-year periodic inspection and operational testing program for 191 fire dampers at its Cincinnati facility (1101 Summit Road, Summit Behavioral Healthcare, Cincinnati, Ohio 45237), with proposals due October 15, 2026. All work must comply with NFPA 80 (Standard for Fire Doors and Other Opening Protectives) and NFPA 101 (Life Safety Code), and the contractor must adhere to hospital-specific Infection Control Risk Assessment (ICRA) guidelines for ceiling access and dust containment in an active healthcare environment.

The scope requires operational testing of each fire damper including fusible-link removal, actuator signaling to closed position, verification of full closure without obstruction, visual inspection of frame and blades for cleanliness and corrosion, cleaning and lubrication of moving parts using manufacturer-approved dry lubricants, and reinstallation and return to open position. The contractor must document deficiencies and perform corrective work as needed. Access assessment, visual inspection for alignment and debris, and compliance with hospital infection control policies during all ceiling-access work are mandatory. The work encompasses 191 fire dampers across the single healthcare facility in Cincinnati, Ohio (Hamilton County and Cleveland City jurisdiction).

No contract value, contract term structure beyond the 6-year inspection cycle, incumbent contractor, evaluation criteria, pre-bid meeting, or question deadline is specified in the source material.

Opportunity text

Scope of Work: 6-Year Hospital Fire Damper Inspection & Testing 1. Project Overview The Objective of this project is to perform the mandatory 6-year periodic inspection and operational testing for 191 fire dampers located at Summit Behavioral Halthcare (1101 Summit Road, Cincinnati, Ohio 45237). All work must comply with NFPA 80 (Standard for Fire Doors and Other Opening Protectives) and healthcare life safety compliance standards. Because this work takes place in an active healthcare environment, the contractor must minimize operational disruption and adhere to strict infection control policies. 2. Applicable Standards & Regulations The Contractor must perform all services in strict accordance with the following regulations:

  • NFPA 80 - Standard for Fire Doors and Other Opening Protectives (specifically sections regarding periodic testing of fire dampers).
  • NFPA 101 - Life Safety Code.
  • Infection Control Risk Assessment (ICRA) - Hospital-specific guidelines for ceiling access and dust containment.

3. Detailed Scope of Services The contractor is required to execute the following phases for all 191 fire dampers: Phase I: Inspection and Testing Procedures For every fire damper, the contractor must perform an operational test matching its design type: • Remove the fusible link. • Signal the actuator to closed position| • Verify full closure without obstruction. • Visually verify complete closure. • Check link for damage/corrosion. • Reset system to normal operations. • Reinstall link and return to open position. • Visually verify return to full open.

  • Access Assessment: Open existing access doors. Ensure the access window is clean, properly sized, and uninhibited.
  • Visual Check: Check the damper frame and blades for cleanliness, corrosion, alignment, and any debris or dynamic interference that might stall operation.
  • Lubrication: Clean and lubricate all moving parts using manufacturer-approved dry lubricants where necessary (avoid oil/grease that attracts dust).

Phase III: Deficiencies and Minor Repairs

  • Minor Adjustments: Resolve minor friction issues, clear small obstructions, or adjust loose linkages on-site during the inspection window.
  • Fusible Links: Replace any melted, corroded, painted, or compromised fusible links immediately.

4. Documentation & Deliverables (AHJ-Ready Report) Upon completion, the contractor must deliver a comprehensive, digital, audit-ready compliance report organized by Damper Asset ID. The report must include:

  1. Inventory Summary: A master list of all 191 dampers showing their location, type, size, and pass/fail designation.
  2. Individual Test Sheets: For every single damper, document:
  3. Specific location (Building, Floor, Room, Grid Line, or Above-Ceiling description).
  4. Date of inspection and name of the qualified inspector.
  5. Damper status (Passed, Failed, or Inaccessible).
  6. "Before" and "After" timestamped photographs showing the damper in both its full-open and full-closed positions.
  7. Deficiency Log: A distinct master list summarizing failed or inaccessible units, along with structural explanations and explicit repair recommendations.

5. Hospital Special Provisions & Safety

  • Badging & Escort: All contractor personnel must check in daily, wear hospital-issued vendor identification badges, and coordinate closely with facility escorts.
  • Cleanup: No tools or trash may be left unattended in hospital.