The City of Kirksville, Missouri is requesting sealed bids for the Rotary Park Connectivity Project (Federal Project No. TAP-3700(213), City Project No. PA-21-001), with bids due October 1, 2026 at 3:00 p.m. at the City Clerk's office, 201 S. Franklin St., and a pre-bid meeting scheduled for September 15, 2026 at 1:30 p.m. at City Hall. Bidders must be on MoDOT's Qualified Contractor List and no second-tier subcontracting is permitted.
The scope encompasses site preparation, removal and disposal of existing improvements (approximately 2,289 square feet), embankment work (61 cubic yards cut, 387 cubic yards fill), concrete sidewalk construction (9,111 square feet of 4-inch thick macro synthetic fiber-reinforced concrete over 4-inch rolled stone base), ADA-compliant sidewalk ramps (471 square feet), handrail installation (60 linear feet), curb and gutter (semi-mountable and square configurations totaling approximately 388 linear feet and 309 square feet), concrete slab (915 square feet of 8-inch thick with 6-inch Type 5 base), storm drainage piping (402 linear feet of 12-inch diameter corrugated HDPE with flared end sections and curb inlets), and landscape restoration including fertilizing, seeding, mulching, and grading (12,783 square feet).
All workers must be paid prevailing wage rates as established by the Department of Labor and Industrial Relations or state wage rates, whichever is higher. The DBE goal is 0%. Successful contractors must comply with all licensing and testing requirements per Kirksville Municipal Code Chapter 12, Article I, Section 12-2, and all on-site employees must complete a 10-hour OSHA construction safety program within sixty days of project commencement. Bidders must submit a certified or cashier's check or bid bond equal to 5% of the proposal amount. Bids may not be withdrawn for sixty days following the opening date. The project is federally funded through the Transportation Alternatives Program. Questions regarding contract documents should be directed to the Engineering Department at 660.627.1225.
Opportunity text
Traffic Control; Approximately 2,289 square feet of Removal & Disposal of Existing Improvements; 61 cubic yards Cut Embankment from City Stockpile; 387 cubic yards Fill Embankment; 9,111 square feet of 4 thick concrete sidewalk Macro Synthetic Fiber Reinforced over 4 rolled stone base; 471 square feet of ADA compliant Sidewalk Ramp Macro Synthetic Fiber Reinforced over 4 rolled stone base; 60 linear feet of Handrail; 63 linear feet 6 Semi-mountable Curb and Gutter; 309 square feet of 2 wide Square Curb and Gutter; 25 linear feet of 3 wide Square Curb and Gutter; 915 square feet of 8 thick concrete slab with 6 thick Type 5 base; 402 linear feet of 12 diameter Corrugated HDPE Storm Pipe; 3 each 12 diameter Flared End Section; 2 each 2x3 Curb Inlet and Basin; 12,783 square feet of fertilizing, seeding, and mulching and related surface restoration including grading.
Files
| File | Type | Posted |
|---|---|---|
| Rotary Park Connectivity Project.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity