PW 2022 Bond Year 3 Contract 13, City Project No. 104311

Closed State & local contract opportunity Posted

Solicitation number
26-0308
State
Texas
Responses due

Opportunity facts

Jurisdiction

Opportunity details come from constructionbidsource.com. Updated .

About this opportunity

The City of Fort Worth, Texas is soliciting sealed bids for public works improvements under PW 2022 Bond Year 3 Contract 13 (City Project No. 104311), with bids due October 1, 2026 at 2:00 p.m. CST via the Bonfire Procurement Portal. A Small Business participation goal is established under City Ordinance No. 27832-08-25 for contracts $100,000 or greater.

The scope encompasses approximately 4,000 linear feet of 8-inch water pipe installation, 5,500 linear feet of 8-inch sewer pipe installation, 9,000 square yards of pulverization and asphalt overlay, 20,800 square yards of concrete pavement, 30,000 square feet of concrete sidewalk, and 33,000 square feet of concrete driveway. Bidders must comply with prequalification requirements for designated work types including paving, water and sanitary sewer construction, CCTV inspection, and auger boring. Contractors must perform at least 35 percent of the contract value with their own organization unless otherwise approved by the City.

Bidders must submit a bid bond equal to five percent of the maximum bid price. Nonresident bidders must comply with Texas Government Code Chapter 2252.001 pricing requirements and provide evidence of authority to conduct business in Texas. All bidders must acknowledge receipt of all addenda and submit Conflict of Interest statements and Certificate of Interested Parties forms prior to contract award. The City will award the contract to the lowest responsible and responsive bidder within 90 days of bid opening.

A prebid conference will be held on Monday, September 14, 2026 at 3:00 p.m. via web conferencing for registered bidders. Public opening and reading of bids will follow immediately after the 2:00 p.m. closing on October 1.

Opportunity text

The major work will consist of the (approximate) following: 4,000 LF - 8 Water Pipe. 5,500 LF - 8 Sewer Pipe. 9,000 SY - Pulverization and asphalt overlay. 20,800 SY Concrete pavement. 30,000 SF Concrete sidewalk. 33,000 SF Concrete driveway.

Files

File Type Posted
2022 Bond Year 3 Contract 13 - TPW 100 Spec Book.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for State & Local Contractors