About this opportunity
The Town of Pulaski, Virginia is soliciting sealed bids for superstructure replacement of the West Commerce Street bridge over Peak Creek, with bids due December 16, 2026 at 2:00 p.m. Bidders must be prequalified with the Virginia Department of Transportation (VDOT) as bridge contractors and must submit a copy of their VDOT Certificate of Qualifications with the bid. Schwartz & Associates, Inc. Consulting Engineers prepared the project manual on behalf of the Town.
The scope covers demolition of the existing superstructure, substructure repair, reconstruction with prestressed concrete bulb-T beams, approach work, and water line replacement across a 70-line-item bid form. Line items include mobilization, maintenance of traffic, cofferdams, dewatering, bridge deck work, railings, riprap, shotcrete, pavement, guardrails, and water line systems of various diameters. The contract requires compliance with VDOT Road and Bridge Specifications (2020) and federal civil rights, labor standards, and environmental provisions. The project is federally funded under State Project 4602-125-124 and Federal Project STP-5125 (127), with a 0% DBE goal.
Bidders must provide evidence of Virginia contractor registration and certify they are not barred from bidding by any Commonwealth agency. The successful bidder must obtain a Town of Pulaski business license before work begins. Bidders must submit a certified check or bid bond equal to 5% of the base bid plus alternates, and the awardee must furnish performance and payment bonds for the full contract amount.
The fixed completion date is August 18, 2028, representing 459 days from notice to proceed, which is expected on or before May 17, 2027. Liquidated damages are assessed at $1,350 per calendar day for delays beyond the completion date. Notice of award is anticipated on or about February 14, 2027. Answers to bidder questions are to be posted by November 25, 2026.
Opportunity text
The Project scope involves the superstructure replacement of West Commerce Street Bridge over Peak Creek. The repairs also include water line replacement and approach work.