About this opportunity
Leon County, Florida is soliciting proposals for engineering and procurement of 115 kilovolt steel monopole transmission structures for the BP-8 and FAMU Way projects, with proposals due July 30, 2026.
The scope requires design and selection of steel monopole transmission structures across three installations: two pier-mounted structures engineered to specified load cases, and one direct-embed structure selected from a catalog LD pole that meets the same loading requirements. The BP-8 structure is modeled on a Meyer LD12 Flange Structure (stock number 1205F3at) and designated as Structure 68, a 94-foot engineered pole that must be designed as a slip-joint structure with two slip joints. Vendors are expected to provide recommendations on ground-sleeve dimensions rather than work from pre-specified values. Design must account for broken-wire load cases and stringing conditions applied to all wires on one side of each structure, with separate load paths for wires ahead and wires behind the pole.
No estimated contract value, contract term, evaluation criteria weighting, incumbent contractor, pre-bid meeting, question deadline, or additional timeline milestones are specified in the source material.
Opportunity text
OVERVIEW Engineer two sperate steel monopole transmission structures that are pier mounted with given load cases. Select an LD pole that satisfies the loading cases for the third direct embed structure. 3.2 ADDITIONAL INFORMATION / CLARIFICATIONS - Ground Sleeve Dimensions are not provided as COT would like vendor recommendations - For both broken wire cases and stringing conditions apply conditions to all wires on one side of the structure • All wires ahead should be considered broken • All wires on the back should be considered broken - BP-8 LD Steel Pole has been modeled using a Meyer LD12 Flange Structure with the stock number 1205F3at - Structure 68 (94 Ft Eng Pole) - Shall be designed as a slip joint structure (2 slip joints).