Parking Lot Painting Renewal – USCG Base New Orleans
Closed State & local contract opportunity Posted
- Solicitation number
- 70Z02926QNEWO00350
- State
- Louisiana
- Responses due
Opportunity facts
- Jurisdictions
Opportunity details come from constructionbidsource.com. Updated .
About this opportunity
The United States Coast Guard Base New Orleans is requesting bids on parking lot painting renewal at 1790 Saturn Boulevard (NASA Michould Assembly Facility) under a Total Small Business Set-Aside, with proposals due August 10, 2026.
This is a small-business-only procurement (NAICS 237310, Highway, Street, and Bridge Construction). The Service Contract Act applies.
The scope includes repainting approximately 260 standard parking spaces, 8 handicap-accessible spaces with stenciled placarding, 37 stenciled GV Parking spaces, one red painted curb with No Parking stencil at the Fire Pump (approximately 120 linear feet), one white painted curb at the main entrance (approximately 40 linear feet), four curbs in front of fire hydrants painted red with No Parking stencils, and renewal of two pedestrian crosswalks totaling approximately 50 linear feet. All work must comply with the Federal Highway Administration Manual on Uniform Traffic Control Devices (MUTCD) and Americans with Disabilities Act (ADA) Standards.
The contractor furnishes all labor, tools, materials, transportation, equipment, supervision, and personnel. Work shall be performed Monday through Friday, 8:00 a.m. to 4:00 p.m., excluding federal holidays, and must be scheduled with the Contracting Officer's Representative (CWO Mike Ackiss). Personnel must hold TWIC, military, or pre-approved identification with minimum 5 business days advance notice for badge creation. All Safety Data Sheets for hazardous materials require pre-approval by Base New Orleans Environmental Protection before work commencement; waste disposal must comply with the Resource Conservation and Recovery Act (RCRA). The contractor is responsible for work-site safety, environmental compliance, site restoration, and any damage to government property.
Upon award, contractors must submit a detailed work schedule, report of findings, quote for further repairs as needed, and Safety Data Sheets within 14 calendar days. The Coast Guard has 7 calendar days to review. Work must begin within 14 calendar days of approval. Final contract acceptance occurs only after the Contracting Officer's Representative approves job-site appearance and cleanliness standards.
Opportunity text
Total Small Business Set-Aside, 237310 - Highway, Street, and Bridge Construction. Contractor to renew all painted surfaces in the parking lots. Work includes repainting approximately 260 standard parking spaces, 8 handicap accessible spaces with stenciled placarding, 37 stenciled GV Parking spaces, one red painted curb with No Parking stencil at the Fire Pump (approximately 120 linear feet), one white painted curb at the main entrance (approximately 40 linear feet), four curbs in front of fire hydrants painted red with No Parking stenciled, and renewal of two pedestrian crosswalks totaling approximately 50 linear feet.
Files
| File | Type | Posted |
|---|---|---|
| Renew_Parking_Lot_Paint_SOW.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity