Jett Industries, Inc. is assembling a bid for the CAT-475 High Level Outlet installation and crest gate removal at Gilboa Dam in St. Lawrence County, New York, with bids due December 24, 2026. The opportunity is designated M/WBE in its title, and the source states prevailing wage applies under the Union Davis Beacon heading.

The work is a two-chambered High Level Release Tower (HLRT) built upstream of the existing Upper Gate Chamber against the dam's upstream face. The HLRT houses hydraulic controls on an enclosed operating floor and includes guide slot assembly, twin bonneted knife gate valves, an air vent pipe, and a removable bar rack that can be swapped for a removable temporary bulkhead. The scope also covers hand-mining a tunnel through the dam, a new conveyance pipe from the HLRT to an outfall structure at the downstream spillway steps, removal of the existing spillway crest gates with their mechanical, electrical, instrumentation, and controls equipment, and backfill of the vacated notch with reinforced mass concrete matching the crest and spillway step pattern. Additional components include fall protection, a waterproof access door, stairways, hatches, and instrumentation upgrades for remote monitoring and control of HLO flow, integrated into the existing SCADA system, with flow monitoring inside the HLRT and at the plunge pool's end sill.

Project documents and scope details are posted to the Files tab on Building Connected. Addenda will be uploaded there and bidders notified through the platform, and bidders must acknowledge addenda in writing on the bid proposal form or quote. Requests for clarification are governed by a deadline tied to a posted date, and the source text truncates before stating it.

Opportunity text

Jett Industries, Inc. (Jett - Contractor) is assembling a bid for the A High Level Outlet (HLO) will be constructed at Gilboa Dam. The HLO intake will be a two‐chambered structure, referred to as the High Level Release Tower (HLRT) housing the hydraulic controls on an enclosed operating floor.The HLRT shall be equipped with guide slot assembly, twin bonneted knife gate valves, an air vent pipe, and a removable bar rack, which can be switched with a removable temporary bulkhead. The HLRT shall be constructed upstream of the existing Upper Gate Chamber (UGC) against the upstream face of the dam. A tunnel will be hand-mined through the dam, a new pipe shall be constructed to convey water from the HLRT to an Outfall Structure at the downstream Spillway steps. The existing Spillway crest gates that occupy the Spillway notch shall be removed along with their ancillary mechanical and electrical equipment, instrumentation, and controls in the UGC. After the gates are removed, the portion of the Spillway presently occupied by the crest gates shall be backfilled with reinforced mass concrete to match the crest and Spillway step pattern. Other components of the Work include installation of fall protection features, a waterproof access door, stairways, and hatches and instrumentation upgrades that include remote monitoring and control of the HLO flow, integrated into the existing SCADA system, and flow monitoring within the HLRT and at the plunge pool's end sill. Union Davis Beacon/Prevailing Wage: Access to Bid Documents Project documents and Scope details will be posted to the Files tab of Building Connected. Issuance of Addenda by Owner Jett will upload to the FILES tab on Building Connected all addenda as received by the Owner. A notification through Building Connected will be sent to Bidders. Bidders are required to acknowledge receipt of addenda in writing on the Bid Proposal form or their quote. Requests for Clarification Any Bidder, no later than the date posted on the Project Information Page, may submit questions for interpretation or clarification of, or addenda to, this Bid. All requests must be submitted in writing and sent by email or as a message through Building Connected The Project includes the following Work: General scope of work includes Additional Project requirements: *All quotes must be submitted through the Building Connected platform. Contact the scope lead if there are any questions or issues with submissions.* Please reach out to ProcurementWCL@kiewit.com for access troubleshooting. Link to Files:https://app.buildingconnected.com/projects/6af34f78366008494e11b637/info Service-Disabled Veteran-Owned Business (SDVOB) SDVOB Goal: 0.00% Minority / Women Business Enterprise contracting goals (MWBE) Total MWBE Goals: 13.00% Disadvantaged Business Enterprise contracting goals (DBE) DBE Goal: 0.00%