About this opportunity
The State of Nebraska is requesting sealed bids for the Merritt Reservoir South project (N-97) in Cherry County, a grading, culvert extension/replacement, and asphalt resurfacing undertaking, with bids due October 1, 2026.
The scope encompasses road improvements and infrastructure modifications at the Merritt Reservoir South location. Prevailing wage requirements apply. Contractors must hold valid Nebraska licensing and provide evidence of prior experience with similar infrastructure projects in the state. Bid submissions must include detailed cost estimates for labor, materials, equipment, and services; required insurance certifications; and contractor licensing verification. All bidders are subject to bonding obligations and contractual insurance minimums.
Award will be made to the lowest responsive and responsible bidder meeting all technical and administrative qualifications. A pre-bid site visit and/or bidders conference may be available for prospective bidders to review project conditions and obtain clarification on scope requirements. Funding derives from State of Nebraska appropriations or allocated capital improvement budgets. Contract performance commences upon execution and continues through project completion.
Opportunity text
2 versions
Update #2 · Latest ·
Description: Asphalt widening & resurfacing of the roadway from 22 feet to 28 feet with 4-foot earth shoulders.
Update #1 ·
Project Scope: Grading, culvert extension/replacement, and asphalt resurfacing.