Morgan City Harbor and Terminal District Port Improvements West Side Dock Expansion

Closed State & local contract opportunity Posted

Solicitation number
H.014774 (322)
State
Louisiana
Responses due

Opportunity facts

Jurisdiction

Opportunity details come from constructionbidsource.com. Updated .

About this opportunity

Morgan City Harbor and Terminal District is requesting sealed bids for the West Side Dock Expansion project, a heavy marine construction undertaking comprising 2.88 acres of concrete laydown and transit area plus a 447-foot by 80-foot pile-supported concrete wharf, with bids due August 13, 2026 at 10:00 a.m. and a pre-bid conference and site tour on August 4, 2026 at 10:00 a.m. at the District office. Award will be made to the lowest qualified responsive bidder within 45 calendar days of bid opening, contingent upon State Bond Commission approval and appropriate state agency concurrence.

The scope includes 18 precast concrete piles and capsills; a 22-inch thick steel-rebar reinforced cast-in-place concrete wharf deck; a timber fendering system with 12 treated timber piles, 12-by-12 treated timber whalers, and galvanized hardware; a 900-foot cantilevered steel sheet pile bulkhead along the northern edge; deep soil mixing improvements to elevation minus 70 feet across the entire laydown area footprint; compacted river sand fill raising existing ground 4 to 5 feet; 12 inches of limestone base course; 16 inches of reinforced concrete for the laydown and transit area; approximately 1,700 linear feet of precast concrete drainpipe with 16 catch basins for subsurface gravity drainage; and two 150-foot steel pump station outfall pipe extensions through the bulkhead.

The estimated base bid cost is $30.577 million. A proposal guaranty of 5 percent of the bid amount, payable to Morgan City Harbor and Terminal District, is required with each submission. Bids must comply with the 2018 Louisiana Department of Transportation and Development General Provisions and be submitted on forms provided by the contracting agency; bidders may submit electronically or by paper copy through Central Auction House. The project engineer is T. Baker Smith, LLC; written questions should be directed to Philip Chauvin, Jr., Senior Construction Manager at philip.chauvin@tbsmith.com. Bid documents and specifications are available for download from Central Auction House, with digital copies at no cost to prime bidders from the engineer's office. Disadvantaged businesses are afforded full opportunity to submit bids without discrimination based on race, color, sex, or national origin.

Opportunity text

The Port of Morgan Citys Western Dock Expansion in total will consist of 2.88 acres of concrete laydown and transit area and 447 ft x 80 ft of pile supported concrete wharf. The proposed wharf will be supported by 18 precast concrete piles and precast concrete capsills. The wharf deck will be constructed with steel rebar reinforced cast in place structural concrete at 22 thick. A timber fendering system composed of 12 treated timber piles, 12x12 treated timber whalers, and galvanized hardware. An approximately 900 ft cantilevered steel sheet pile bulkhead will be installed along the Northern edge of the proposed Wharf and will delineate between the Wharf and proposed concrete laydown area. The existing ground below the laydown area will require soil improvements in order to handle the anticipated traffic, equipment, and storage loadings. These improvements will consist of a deep soil mixing program below the entire laydown area footprint to Elevation -70.0 to strengthen the existing in situ soils. Once improved, additional granular material (river sand) will be hauled and compacted in to raise the existing ground approximately 4-5 feet. 12 of Limestone base course will then be installed as the final layer to support the 16 steel rebar reinforced cast in place concrete for the laydown/transit area. Subsurface gravity drainage is to be installed just North of the proposed bulkhead to drain the paved areas, as well as between the existing federal flood protection and edge of the laydown area. The gravity drainage system will consist of approximately 1700 ft of precast concrete drainpipe and 16 precast concrete catch basins. Finally, 2 steel pump station outfall pipes will be extended through the proposed bulkhead. Each extension is approximately 150 ft. This will allow for the existing pump station to discharge into Bayou Boeuf.