About this opportunity
The state of Virginia, specifically Mathews County, is seeking proposals for the Madison Wastewater Treatment Plant (WWTP) Upgrade & Expansion Project, with a contract opportunity ID of 6828dd69ba797d6dfb0bb4a2. The procurement involves a comprehensive upgrade of the existing WWTP, expanding its capacity from 80,000 to 160,000 gallons per day (gpd). Key project elements include installing a new influent fine screening system, flow measurement flume, pump station, Sequential Batch Reactor (SBR) treatment system, blower system, chemical feed and storage systems, UV disinfection system, effluent pump station, sludge dewatering system, electrical infrastructure, generator, and a new SCADA system. A mandatory pre-bid conference is scheduled for May 27th, 2025, at 10:30 AM at the project site, with proposals due by June 12th, 2025. The project requires comprehensive engineering and construction capabilities to deliver a fully functional wastewater treatment infrastructure upgrade.
While specific set-aside designations are not explicitly detailed in the provided documentation, the project appears to be a significant municipal infrastructure investment that would likely be open to qualified engineering and construction firms with demonstrated expertise in wastewater treatment plant design and construction. The project's complexity suggests potential opportunities for local or regional contractors with specialized municipal infrastructure experience. The scope of work indicates a substantial capital investment, though precise budget ranges are not specified in the current documentation. Prospective bidders will need to demonstrate technical competence in designing and implementing advanced wastewater treatment systems, including experience with SBR technologies, electrical systems, SCADA integration, and municipal infrastructure project management. The project represents a significant infrastructure upgrade for Mathews County, requiring comprehensive engineering, construction, and systems integration capabilities.
Opportunity text
2 versions
Update #2 · Latest ·
The project entails upgrading and expanding the Madison WWTP from 80,000 to 160,000 gpd. The major elements of work to be performed include: New influent fine screening system with manual screening chamber; new influent flow measurement flume, new influent pump station, new SBR treatment system to include pre-cast post-tensioned tank system (Pre-EQ, SBR 1, SBR2, Aerobic Sludge Holding 1 and 2 tanks), new SBR and aerobic sludge holding blower system, new chemical feed and storage systems, new UV disinfection system; new effluent pump station with post aeration; new sludge dewatering system and new building; new electrical building/gear/system; new generator with 1,250 gallon belly tank; new ATS, new SCADA system for all new processes/equipment, a new control building and all required ancillary components required to provide a complete and functional system.A mandatory pre-bid conference was held at the project site on May 27th, 2025 at 10:30 AM.
Update #1 ·
The project entails upgrading and expanding the Madison WWTP from 80,000 to 160,000 gpd. The major elements of work to be performed include: New influent fine screening system with manual screening chamber; new influent flow measurement flume, new influent pump station, new SBR treatment system to include pre-cast post-tensioned tank system (Pre-EQ, SBR 1, SBR2, Aerobic Sludge Holding 1 and 2 tanks), new SBR and aerobic sludge holding blower system, new chemical feed and storage systems, new UV disinfection system; new effluent pump station with post aeration; new sludge dewatering system and new building; new electrical building/gear/system; new generator with 1,250 gallon belly tank; new ATS, new SCADA system for all new processes/equipment, a new control building and all required ancillary components required to provide a complete and functional system.A mandatory pre-bid conference will be held at the project site on May 27th, 2025 at 10:30 AM.