Headworks facility, diversion structurea, and diversion structure B rehabilitation project

Closed State & local contract opportunity Posted

Solicitation number
ITB-24-007-00137-0-2025/SA
State
Florida
Responses due

Opportunity facts

Jurisdictions

Opportunity details come from network.demandstar.com. Updated .

About this opportunity

Bids were solicited for the Headworks Facility, Diversion Structure A, and Diversion Structure B Rehabilitation Project in Palm Beach County, Florida, with the bid deadline set for August 8, 2025. The opportunity was posted June 30, 2025, and that deadline has passed. The source names no set-aside, preference, or eligibility restriction.

The Work furnishes all labor, materials, and equipment for concrete rehabilitation, PVC liner work, and minor stucco patching at the Headworks Facility. Headworks scope also includes replacing one rolling door, three doors, one floor access hatch and frame, and channel access cover gaskets; installing two slide gates; and removing existing stop log channels. At Diversion Structure A, the Work covers epoxy rehabilitation and lining of concrete surfaces, replacement of two weir gates and one pump plate, replacement of a 36" butterfly valve with owner-furnished equipment, reinstallation of aluminum railings, and surface preparation and re-coating of exterior concrete. Diversion Structure B requires replacing one weir gate and re-coating exterior concrete surfaces. Exterior re-coating at the Headworks Facility is an alternate. Construction includes dewatering, bypassing, phasing, sequencing, testing, and restoration for a complete operating system. The Work sits on private property owned by the District.

The listed jurisdictions are Palm Beach County and Bay Pines CDP.

Opportunity text

The work for the Headworks Facility, Diversion Structure A, and Diversion Structure B Rehabilitation Project consists of furnishing all labor, materials, equipment, and all incidentals and appurtenances per the Contract Documents for the rehabilitation of concrete surfaces, PVC liners, and minor stucco patching and repair at the Headworks Facility; the replacement of one rolling door, three doors, one floor access hatch and frame, and channel access cover gaskets at the Headworks Facility; the installation of two slide gates at the Headworks Facility; the removal of existing stop log channels at the Headworks Facility; the rehabilitation of concrete surfaces and concrete lining with epoxy at Diversion Structure A; the replacement of two weir gates and one pump plate at Diversion Structure A; the replacement of a 36" butterfly valve with owner furnished equipment at Diversion Structure A; the reinstallation of aluminum railings with base plates and anchor bolts at Diversion Structure A; the surface preparation and re-coating of all exterior concrete surfaces at Diversion Structure A; the replacement of one weir gate at Diversion Structure B; and the surface preparation and re-coating of all exterior concrete surfaces at Diversion Structure B. The surface preparation and re-coating of all exterior concrete surfaces at the Headworks Facility will be considered as an alternate for the Work. Construction also includes dewatering, bypassing, phasing, sequencing, testing and all restoration work for a complete operating system. The Work will be on private property owned by the District.