Palm Beach County's Capital Improvements Division is soliciting sealed bids for the Evidence Building AHU 6 Refurbishment (P-2025-000143), with a mandatory pre-bid conference on December 11, 2026 at 10:00 a.m. and bids due January 7, 2027 at 2:00 p.m. Bidders must be qualified under the county's Annual Contract - HVAC Services, with qualification applications due at least 10 days before the bid due date.

The work modifies Air Handler Unit 6 and includes installing a fourth air-cooled chiller (Trane CH-4), concrete housekeeping pads and grade beams, a reinforced CMU protective screen wall with painted finish, security fencing and gates, and a 30-foot-wide saw-cut opening in the west screen wall. Mechanical and electrical scope covers removing and replacing supply and relief fans and their VFDs, adding a water-cooled heat recovery glycol chiller with pumps and piping, retrofitting fan arrays, and relocating the control panel. The contractor also provides startup under the Commissioning Agent's direction and all BAS integration, programming, and testing. Work must comply with the Florida Building Code. Employees require Critical Facilities and CJI Facilities background clearances, and submittals require a signed non-disclosure agreement covering confidential plans and specifications. The contractor handles site preparation, temporary protection, temporary cooling during chiller replacement, daily cleanup, and hazardous material disposal, and must deliver a Certificate of Occupancy or Certificate of Completion before final payment.

Submittals must include OSBD Schedules 1 and 2, documenting all subcontractors and Small Business Enterprise (SBE) participation. Bid security of at least 5% of the bid price is required for bids of $200,000 or more, in the form of a cashier's check, certified check, money order, or bid bond. A public construction bond equal to 100% of the work order is due within 14 calendar days of award notification.

The contract term is 360 calendar days from Notice to Proceed, with liquidated damages of $180 per day for failure to achieve substantial completion. The warranty covers equipment and materials for 12 months and compressors for 10 years. Work is performed at the Evidence Building, 3075 Gun Club Road, West Palm Beach, Florida.

Opportunity text

SCOPE OF WORK To modifications to Air Handler Unit (AHU) - 6 per the project requirements provided below and the architectural drawings and specifications included as Exhibit 1: a. Contractor shall provide and install a new fourth air-cooled chiller (CH-4 by Trane) b. Contractor shall install new concrete housekeeping pad to support the new air-cooled Page 2 of 5 chiller c. Contractor shall provide new clean and compacted fill. d. Contractor shall provide and install new continuous concrete grade beams to support a new perimeter reinforced CMU protective screen wall with primed and painted cement plaster finish. e. Contractor shall provide and install new 57 Rock base to fill the surface area between the new housekeeping pad and the new screen-wall. f. Contractor shall provide and install new security fencing and gates. g. Contractor shall provide and install new 30 wide x 70 high saw cut opening in the west screen-wall of the mechanical yard for access to the main mechanical yard. h. Mechanical and Electrical modifications include: 1) Removal of existing supply fan, relief fan, and Variable Frequency Drive (VFD)s associated with AHU 6. 2) Demolish and removal of relief fan RF-6 and supply fan SF-6 VFDs 3) Relocate the Electrical Disconnect for AHU 6 energy wheel 4) Provide and install new water-cooled heat recovery glycol chiller, pumps, piping and associated components and accessories. Provide and install new / retrofit fan arrays for the multi fan Supply and Relief Fans 5) In addition, there are a number of mechanical and electrical tasks detailed on the attached drawings to provide a complete and fully operational system. 6) Provide start up services in accordance to the direction of the Commissioning Agent. 7) Provide all required BAS system integration, programing and testing required to make the system fully operational per the engineers plans and specifications. Scope Includes: Relocation of existing control panel to updated location per sheet M201. Provide all piping and low voltage control wiring to make system fully operational. Integration of all new points into the existing Automated Logic WebCTRL system, including graphics, alarms and trends. Point-to-point checkout, functional testing, as-built documentation, commissioning and owner training. The buildings existing BAS is Automated Logic, serviced by Wisch and Jackson. For a proposal per the plans, specifications, and Field Bulletins 84 and 85, contact Sam Haun at Wisch and Jackson, (561) 602-6436. 8) Provide temporary cooling during the chiller replacement period. 9) Salvage existing chiller. 10)Provide coil coating (Heresite) for applicable equipment.

Files

File Type Posted
palm beach P-2025-000143 IFQ Package no plans.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for State & Local Contractors