Electric Capital Improvement Project South Oliver Line Rehabilitation Project
Open State & local contract opportunity Posted
- Solicitation number
- PE-66412-NONST-2027-000000019
- State
- Georgia
- Responses due
Opportunity facts
- Jurisdiction
- NIGP codes
- UNSPSC codes
- 72151502 Electric power system construction service
- 81102402 High voltage overhead line maintenance and repair
- 72141126 Underground utilities construction service
- 72151506 Switchgear and related devices installation service
- 72141111 Gas main construction service
- 72141113 Oil and gas pipeline construction service
- 72141114 Pipeline wrapping service
- 72151503 Cogeneration plant construction service
- 81102401 High voltage overhead line construction
- 72141110 Oil and gas branch line construction service
Show all 19
- 95121641 Pumping station
- 72141122 Electric power line construction service
- 72151504 Computer power conditioning service
- 72151505 Standby or emergency power installation service
- 95121800 Utility buildings and structures
- 72141112 Natural gas compressor station construction service
- 95121803 Nuclear power station
- 95121802 Substation
- 95121801 Radar station
- Point of contact
-
- Devan Seawright dseawright@cityofelberton.net
Opportunity details come from ssl.doas.state.ga.us. Updated .
About this opportunity
The City of Elberton, Georgia, is soliciting sealed bids for rehabilitation and reconstruction of approximately 8,100 linear feet of three-phase primary electrical distribution line under its South Oliver Line Rehabilitation Project, with bids due to the City Clerk's Office by 2:00 p.m. on December 2, 2026. The project is funded through the Georgia Environmental Finance Authority with U.S. Department of Energy federal assistance under the Infrastructure Investment and Jobs Act, and the Notice to Proceed will not issue until GEFA concurrence and all required federal approvals and environmental clearances are obtained. No set-aside or preference program is stated.
The scope covers replacing existing utility poles, upgrading primary conductors to a larger size, and providing all associated labor, equipment, and construction activities along the right-of-way that parallels State Highway 77 and Mineral Springs Road, both inside and outside city limits. The City furnishes poles, pole line hardware, and conductor. The contractor must obtain Georgia 811 utility locates and perform to Electric Cities of Georgia distribution standards, the National Electrical Safety Code, and OSHA 29 CFR 1926 Subpart V and 1910.269. Bidders must submit three references for similar overhead distribution projects completed within the last five years. Build America, Buy America requirements apply to permanently incorporated materials, with manufacturer or supplier certifications due before installation. Davis-Bacon prevailing wages apply, with rates in Exhibit C, and certified payrolls are due through LCPtracker within seven days after each pay period.
The bid is a lump sum with unit prices for additions or deletions, and it must include all labor, equipment, mobilization, traffic control, bonds, insurance, and federal compliance costs. A bid bond or certified check equal to 5 percent of the bid price accompanies each bid, and bids remain firm for 90 days after opening. The successful bidder furnishes performance and payment bonds each equal to 100 percent of the contract price, plus commercial general liability of $1 million per occurrence, automobile liability of $1 million combined single limit, and a $5 million umbrella. Payment is monthly on approved pay applications, less 10 percent retainage until 50 percent of work is complete. Work must commence within 45 calendar days of the Notice to Proceed and finish within 180 calendar days of that date. A pre-bid conference is not mandatory, but bidders are encouraged to contact Brad Alexander, Electric Distribution Manager, to schedule site visits. A notarized Georgia E-Verify contractor affidavit is also required.
Opportunity text
The City of Elberton intends to rehabilitate and reconstruct a section of its electric distribution system. The project consists of approximately 8,100 linear feet of three phase primary electrical distribution line. The scope of work includes, but is not limited to, the replacement of existing utility poles, the upgrading of existing primary conductors to a larger conductor size, and all associated labor, equipment, incidental materials not furnished by the City, and construction activities necessary to complete the project. The distribution line right-of way generally parallels State Highway 77 and Mineral Springs Road. All work shall be performed in accordance with the Electric Cities of Georgia (ECG) distribution construction standards or equivalent standards approved in writing by the City¿s Electric Distribution Manager, and in compliance with the National Electrical Safety Code, OSHA 29 CFR 1926 Subpart V, and 29 CFR 1910.269.
Files
| File | Type | Posted |
|---|---|---|
| Elberton South Oliver RFB.pdf | ||