Greenlawn Water District is requesting bids for wellhead treatment construction at Well No. 5 to address 1,4-dioxane contamination, with bids due October 26, 2026 and a mandatory pre-bid walkthrough on October 14 at 1:00 p.m. at the project site (corner of Wicks Road and Larkfield Road, Commack, New York). This is a prevailing wage, tax-exempt project requiring NYS Apprenticeship Program participation.

MWBE and SDVOB participation goals are 30% and 6%, respectively. The procurement is structured as Multiple Prime, and OSHA cards are required.

Bidders must carry Commercial General Liability Insurance of $2 million per project and $2 million Products and Completed Operations coverage, $1 million Personal and Advertising Injury, $50,000 Fire Damage, and $10,000 Medical Expense. Owners Contractors Protective Insurance of $1 million per occurrence and $2 million aggregate is required in the name of the Water District. Umbrella/Excess Liability Insurance of at least $5 million must be maintained for the contract term, providing "following form" coverage over underlying Commercial General and Automobile liability.

The Architect in Charge is H2M Architects & Engineers (538 Broad Hollow Road, 4th Floor East, Melville, New York; telephone 631-756-8000); the Construction Manager is TBARFI. The project location is Greenlawn Well No. 5 at 90 Wicks Road, Commack, New York (Suffolk County). Questions and clarifications are due October 21, 2026 at 12:00 p.m.

Opportunity text

NYS APPRENTICESHIP PROGRAM REQUIRED Preferred Construction will be bidding forMultiple Prime: Greenlawn Water District - Wellhead Treatment for 1,4-Dioxane at Well No. 5Goal Requirements for MWBE: 30% SDVOB: 6% This is a Prevailing Wage - Tax Exempt Project - OSHA CARDS NEEDEDH2M Project No.: GLWD2501 Requested by: Monday Oct 26 Insurance Coverage: Commercial General Liability Insurance$2,000,000 per Project$2,000,000 Products and Completed Operations $1,000,000 Personal and Advertising Injury$50,000 Fire Damage$10,000 Medical Expense Owners Contractors Protective (OCP) Insurance:The CONTRACTOR shall also provide an Owners and Contractors Protective Liability insurance policy until the completion of all work under this contract, in limits of $1,000,000 per occurrence and $2,000,000 aggregate for bodily injuries and property damages written in the name of the WATER DISTRICT as the sole policyholders. Such insurance shall include a clause making the CONTRACTOR solely responsible for paying the premium thereon. Umbrella/Excess Liability InsuranceUmbrella Insurance - In addition to the above required insurance, the CONTRACTOR and any SUBCONTRACTOR shall provide and maintain an Umbrella Liability Insurance Policy containing a limit of no less than $5,000,000 for bodily injuries and property damages for the life of this contract. Such insurance shall, at least, provide "following form" coverage for underlying Commercial General and Automobile liability coverage otherwise required in these clauses. (Insurance Coverage please read pages 60-63)Architect in Charge: H2M Architects & EngineersTBA 538 Broad Hollow Road4th Floor East Melville, NY 11747 Tel: (631) 756-8000 Construction Manager in Charge: TBARFI Deadline - October 21, 2026 at 12:00pm Project Location: Greenlawn Well No 5 - (Suffolk)90 Wicks RdCommack, NY 11725 Prebid Walkthrough:walk through will be held 10/14/26 at 1:00 PM at the project site, corner of Wicks Road and Larkfield Road in Commack NY. Bid Break downPlease include the below "Breakout Costs" for the following project components. G-1 : Lump Sum Cost UNIT Pricing Unit Price 1 : N/A Click THIS LINK for Dropbox to Plans and Specifications Scope of BidGround up new 1,500 SF AOP/GAC Masonry Building ScheduleGuesstimate on Schedule - Will ask at WalkthroughTentative Contract Award: TBDSubmittals/Shop Drawings: Start Date: NTP - 30 DaysConstruction starts: TBDSubstantial completion: Start Date: NTP - 450 DaysFinal Punch List/ Closeout: 30 Days after Date of Completed Work Approval Please contact Estimating at estimating@prefconst.com with any questions.Unfortunately, we are not always in the office. We will respond to ALL emails. Service-Disabled Veteran-Owned Business (SDVOB) SDVOB Goal: 6.00% Minority / Women Business Enterprise contracting goals (MWBE) Total MWBE Goals: 30.00%