About this opportunity

San Bernardino County Department of Public Works - Special Districts is soliciting bids for streetlight construction along Cedar Avenue and Santa Ana Avenue in Bloomington, California, under Project No. 30.30.0225 for County Service Area SL-1, with bids due December 16, 2026. Eligibility depends on compliance with California public works requirements: contractors must register with the Department of Industrial Relations under Labor Code section 1725.5, pay prevailing wages under Labor Code sections 1770 et seq., and submit certified payroll records monthly to the Labor Commissioner. The source names no set-aside or local-vendor preference.

The contractor must furnish all materials, labor, equipment, and services to deliver a fully operational streetlight installation. The bid package incorporates technical specifications covering LED fixtures, poles, foundations, electrical systems, and hardware, with work meeting the California Electrical Code, California Building Code, and ASTM standards. Apprenticeable crafts require one apprentice hour for every five journeyman hours unless exempted, and overtime applies at 1.5 times the basic rate beyond eight hours daily or 40 hours weekly. Prevailing wage violations carry penalties of $25 to $200 per worker per day.

Final completion is due within 60 calendar days of the Notice to Proceed, with liquidated damages of $1,000 per calendar day for delays. The contractor must furnish a Performance Bond and a Labor and Material Payment Bond, each at 100 percent of the Contract Sum, plus a one-year Maintenance Bond at 10 percent. Required insurance includes general liability of $1 million combined single limit, automobile liability of $1 million ($2 million if transporting passengers), continuing products and completed operations liability of $5 million for projects over $1 million, workers' compensation, builder's risk, and umbrella coverage. Insurance documents and bonds are due within 10 calendar days of award, and each day of delay deducts one day from contract time. Payment is capped at 95 percent of the Contract Sum until Final Completion, with final payment 60 days after the Notice of Completion is filed, made by electronic fund transfer. The one-year warranty runs from Final Completion.

Post-award milestones include an initial conference within 10 calendar days of commencement and submission of project schedules, submittal schedules, procurement schedules, and schedules of values within 14 calendar days after commencement.