About this opportunity
The Pennsylvania Department of Transportation (PennDOT) is soliciting bids for a precast reinforced concrete box culvert, approach roadway, and guide rail over Camp Run on State Route 3001 in Potter County, with bids due December 10, 2026 at 11:00 AM. Prequalification is required, and the project carries prevailing wage requirements, Pennsylvania prevailing wage act compliance, and equal employment opportunity provisions tied to prequalification. The project is 100% state-funded with no federal involvement.
The scope covers furnishing and placing a 15.0' x 3.5' precast box culvert with inlet and outlet sections, constructing approach and roadway using Superpave asphalt mixture designs for binder and wearing courses, and installing guide rail and miscellaneous items across approximately 625 linear feet (0.12 miles) on SR 3001 (E. Fork Road) in Wharton Township, south of Conrad. Structure work comprises 35% of the total scope. Quantities include approximately 715 tons of subbase, 798 tons of asphalt mixtures, and more than 2,000 square yards of geotextile. The project requires erosion and sediment pollution control, stormwater management, infiltration testing, and four days minimum advance traffic notification.
The project cost range is $200,000 to $499,999.99. The anticipated Notice to Proceed is January 25, 2027, with required completion by August 11, 2027. Pipe delivery and box culvert installation are scheduled for July 15, 2027 with Jason Belsole, Potter County Maintenance Manager, and paving completion is required by July 28, 2027. Road user liquidated damages are $3,000 per day for delays in box culvert delivery and installation after July 15, 2027.
Opportunity text
The description and location of the project is as follows: This work is the furnishing and placement of an 15.0' x 3.5' precast reinforced concrete box culvert and inlet and outlet sections over Camp Run at a Department prepared site, construction of approach and roadway consisting of Superpave Asphalt Mixture Designs for the binder and wearing courses and furnishing and placement of guide rail, and miscellaneous construction all within a length of approximately 625 linear feet (0.12 miles) as indicated on the approved drawings included in the bid package for State Route 3001 Section A05, in Potter County, Wharton Township. On SR 3001 (E. Fork Road), from Segment 0150 Offset 0540 to Segment 0150 Offset 1120. Location is south of Conrad.